The construction of 400 kV + 110 kV transmission line Alajärvi - Petäjävesi
Awarded
The competition has ended and a winner has been selected.
- Qualification deadline
- Nov 20, 2025Expired
- Award
- Price only
Brief
Fingrid Oyj has entered into an agreement with Enersense PN Oy for the construction of a 400 kV + 110 kV transmission line between Alajärvi and Petäjävesi substations, including necessary modifications to the existing network. The 110 kV line ends at the substations, while the 400 kV line bypasses both stations. The line route is approximately 100 km long and is located in Satakunta. The contract has a value of 26,468,700 €.
Elektrisk infrastruktur og veibelysning
Result
- Enersense PN OyWinner
- 4Number of bids
- €26,468,700Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Alin hinta + laatupisteet
Source
No source found in the documents. Check the weight against the tender documents.
Description
Kokonaispisteet
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Fingrid Oyj
From the notice
Fingrid Oyj is requesting Tender for the construction of transmission line 400 kV + 110 kV between Alajärvi and Petäjävesi substation along with necessary modifications to the existing network. The 110 kV line ends at the substations but the 400 kV line bypasses both stations. The length of line route is app. 100 km.
Contact
Rami Isomäkirami.isomaki@fingrid.fi- Result · PrequalificationType
- SatakuntaLocation
- 45311000Main codeElectrical wiring and fitting work