    1. Competition notice published

      Mar 27, 10:35 PMMarch 27, 2024 10:35 PM
    2. Supplier selection

      May 22, 12:00 AMMay 22, 2024 12:00 AM
    3. Contract signed

      Jun 24, 12:00 AMJune 24, 2024 12:00 AM
    4. Result notice published

      Sep 26, 6:35 AMSeptember 26, 2024 6:35 AM

    Brief

    Iceland: Tenders/Gardabaer/The third phase of the construction of Urridaholt School

    Awarded

    The competition has ended and a winner has been selected.

    Brief

    Bygningsarbeid og installasjoner

    Urridaholts School is a new School for children in the age of 6 to 15 and part of the building is a kindergarten for children in the age of 1 to 6. The building has two floors and a basement. The second phase of the building has just been completed. The third phase includes extra classrooms, gymnasium and indoor swimming pool along with associated rooms as locker rooms, technical rooms and etc. Phase three is a continuation of the second phase and is consistent with the first and second phases regarding architecture and construction solutions. The main structural parts, walls, slabs and roof, are made of cast-in-place concrete. The walls are isolated from the outside and mainly covered with aluminum sheets but partly with timber. The roof is flat and isolated and covered with membrane and grass. The aim is to obtain Breeam certification for the building. Earthworks for the third phase have been partially completed. The total floor area of the 3rd phase of Urriðaholt School is 3,800 m2. The main quantities for the construction of the structural part of the third phase of the building are: • Forms for cast-in-place concrete: 13.136 m2 • Rebars: 249.195 kg • Concrete: 2.245 m3 The last day of delivery is 17th of April 2026.

    Result

    Winner
    Tharfathing
    Number of bids
    4
    Contract value
    ISK 2,444,323,458

    About the bid

      Urridaholts School is a new School for children in the age of 6 to 15 and part of the building is a kindergarten for children in the age of 1 to 6. The building has two floors and a basement. The second phase of the building has just been completed. The third phase includes extra classrooms, gymnasium and indoor swimming pool along with associated rooms as locker rooms, technical rooms and etc. Phase three is a continuation of the second phase and is consistent with the first and second phases regarding architecture and construction solutions. The main structural parts, walls, slabs and roof, are made of cast-in-place concrete. The walls are isolated from the outside and mainly covered with aluminum sheets but partly with timber. The roof is flat and isolated and covered with membrane and grass. The aim is to obtain Breeam certification for the building. Earthworks for the third phase have been partially completed. The total floor area of the 3rd phase of Urriðaholt School is 3,800 m2. The main quantities for the construction of the structural part of the third phase of the building are: • Forms for cast-in-place concrete: 13.136 m2 • Rebars: 249.195 kg • Concrete: 2.245 m3 The last day of delivery is 17th of April 2026.

      Contact name
      Umhverfissvid Gardabaear
      Contact phone
      +354 525 8500
      Contact email
      gardabaer@gardabaer.is

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

    • Description

      The lowest bidder that fulfills all requirements is chosen

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    Gardabaer
    Title
    The third phase of the construction of Urridaholt School
    Type
    ResultPrequalification
    Main code
    45000000Construction work
    Supplemental codes
    45400000Building completion work
    Location
    Höfuðborgarsvæði
    Duration
    22 months

    Active similar competitions

    • HBD - Amt für Hochbauten (AHB)

      Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

      BAV 80753 Schulanlage Saatlen, Ersatzneubau - BKP 461 Erd- und Unterbau

      Das Amt für Hochbauten (AHB) benötigt Bauarbeiten für den Ersatzneubau der Schulanlage Saatlen, spezifisch für den Erd- und Unterbau (BKP 461). Die Zuschlagskriterien basieren auf Qualität.

      CompetitionSep 4, 2026
      Oct 15, 2026(4 days)
    • Oslobygg Kf

      Bygg og anlegg - Oppføring og konstruksjon av bygninger

      Anskaffelse av totalentreprise Hovseter – ny spesialavdeling

      Oslobygg Kf trenger en totalentreprise for å etablere en ny spesialavdeling på Hovseter skole i Oslo, med et samlet bruttoareal på 1234 m² fordelt over to etasjer, samt et teknisk rom på tak. Bygget skal oppføres i massivtre med synlige treoverflater og utvendig aluminiumskledning, og skal oppfylle krav til plusshusstandard. Det skal også opparbeides et eget uteområde. Prosjektet krever robuste og tilpassede løsninger for elever med diagnoser innenfor autismespekterforstyrrelser. Tildelingskriteriene er pris (70%), tilbudt personells kompetanse og erfaring (10%) og oppdragsforståelse (20%).

      CompetitionOct 8, 2026
      Oct 14, 2026(3 days)
    • HBD - Amt für Hochbauten (AHB)

      Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

      BAV 80753 Schulanlage Saatlen, Ersatzneubau - BKP 421 Gärtnerarbeiten

      Das Amt für Hochbauten (AHB) benötigt Gärtnerarbeiten für den Ersatzneubau der Schulanlage Saatlen in der Schweiz. Die Vergabe erfolgt auf Basis von Qualitätskriterien.

      CompetitionSep 4, 2026
      Oct 15, 2026(4 days)
    • HBD - Amt für Hochbauten (AHB)

      Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

      BAV 80720 Schulanlage Tüffenwies, Neubau - BKP 277.2 Feststehende Elementwände

      HBD - Amt für Hochbauten (AHB) benötigt Bauarbeiten für feststehende Elementwände im Rahmen des Neubaus der Schulanlage Tüffenwies. Die Zuschlagskriterien basieren auf Qualität.

      CompetitionSep 18, 2026
      Oct 29, 2026(18 days)
    • HBD - Amt für Hochbauten (AHB)

      Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

      BAV 80926 Schulanlage Entlisberg, Erweiterung - BKP 212.2 Elemente aus Beton

      HBD - Amt für Hochbauten (AHB) benötigt Bauarbeiten für die Erweiterung der Schulanlage Entlisberg, spezifisch für Betonelemente (BKP 212.2). Die Zuschlagskriterien basieren auf Qualität.

      CompetitionOct 2, 2026
      Nov 11, 2026(31 days)