Search
  • Search


Germany: Tenders/Stadtwerke Görlitz AG/UNITED HEAT Wastewater Heat Pump - EPC-Contractor - Detailed Engineering and Construction
  1. Planning notice published

    Jul 22, 12:39 PMJuly 22, 2026 12:39 PM
  2. Planned competition start

    Sep 1, 12:00 AMSeptember 1, 2026 12:00 AM
  3. Contract start date

    Jan 1, 2027 12:00 AMJanuary 1, 2027 12:00 AM
  4. Contract end date

    Dec 29, 2028 12:00 AMDecember 29, 2028 12:00 AM

Brief

UNITED HEAT Wastewater Heat Pump - EPC-Contractor - Detailed Engineering and Construction

Planned

The competition has not been announced yet.

Deadline
Sep 1,Expired
Agreement
Construction workuntil Dec 2028

Brief

Stadtwerke Görlitz AG is planning the procurement of an EPC contract for a wastewater heat pump, including detailed engineering and construction, to connect the existing district heating systems of Görlitz and Zgorzelec. The buyer is seeking capable EPC contractors or consortia with demonstrable expertise in large-scale heat pumps, energy centers, industrial plant construction, and complex interface management, who can design, manage, and deliver complex energy and infrastructure projects as integrated systems. Interested companies are encouraged to prepare for the subsequent procurement documents, which will set out binding requirements.

Anleggs- og infrastrukturbygging

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Stadtwerke Görlitz AG

From the notice

  • Description of the Scope of Services Project: The United Heat project will connect the existing district heating systems of Görlitz and Zgor-zelec to create a shared cross-border heat network. The German and Polish networks will be thermal-ly interconnected, enabling heat transfer in both directions. Further information on the planned en-ergy mix and generation concept is available at: https://united-heat.com/de/. Purpose of this Prior Information Notice: This notice informs suitable companies at an early stage about the planned procurement of the work packages described below. It serves as an initial market approach and allows interested companies to prepare in good time. Binding requirements will be set out only in the subsequent procurement documents. Description: The generation and interconnection site at "Klärwerk Nord" is a key element of United Heat. Its objective is to provide climate-neutral district heating and establish, in the longer term, a cross-border thermal link between the district heating systems. • WP 12 covers the connection to a separate cross-border district heating pipeline to be con-nected at a later stage, including pipeline installation and civil works. • WP 20 covers the large-scale wastewater heat pump, including water abstraction and return, the energy centre, electrical, instrumentation and control systems, and integration into the district heating network. The two work packages will be considered together to combine technical optimisation, permitting feasibility, security of supply, construction sequencing and the operating concept within one inte-grated approach. The contract is intended to be awarded to a general contractor or capable consorti-um. • Design and optimisation: Review and further development of the reference design, detailed engineering and optimisation within the functional requirements. • Plant and infrastructure delivery: Construction of the heat pump energy centre, heat ex-changers, piping, route sections, power supply, instrumentation and control / supervisory control systems and civil infrastructure, including site management, construction supervision and HSE. • Interface management: Coordination with the district heating network, wastewater treat-ment plant operations, grid connection, higher-level control systems, SCADA / supervisory systems and adjacent work packages. • Permitting management: Compliance with permit conditions relating to construction, envi-ronment, noise, fire safety, water law and plant-specific safety. • Commissioning and verification: Functional testing, trial operation, optimisation, verifica-tion of agreed functionalities, training of the Employer’s personnel and defect rectification. • Additional services: Preparation of supplementary operational documentation, including timely service agreements based on a service level agreement. Project status: Interested companies will receive a reference design comprising preliminary and per-mitting design documentation, explanatory reports, site and route plans, plant layouts, process flow and hydraulic diagrams, functional descriptions, information on existing assets, utilities and site con-ditions, instrumentation and control / building automation documentation, function lists and rele-vant electrical, instrumentation, control and grid connection information. The documents enable a sound technical assessment and serve as a starting point for Contractor optimisation. They are a ref-erence and information basis. The subsequent procurement is intended to define functional re-quirements and binding minimum quality standards while allowing technically appropriate optimisa-tion by the Contractor. Outlook: Tenderers will receive a functional performance specification. On this basis, the future Con-tractor will be responsible for further design, optimisation, procurement, construction, commission-ing and handover. The Contractor may use the advanced reference design made available during the procedure and may amend it where appropriate and economically advantageous. The project targets companies with strong engineering and management capabilities: the existing project basis reduces familiarisation and assessment risks while allowing proprietary technical solutions, commercial opti-misation and professional EPC delivery. Expected profile of interested companies: The aim is to attract capable EPC contractors / general contractors and suitable consortia experienced in energy centres, large-scale heat pumps, district heating, industrial plant construction and complex interface management. The opportunity is di-rected at companies able to design, manage and deliver complex energy and infrastructure projects as integrated systems. Demonstrable expertise in several of the following areas is required: - Large-scale heat pumps, energy centres, industrial heating and cooling plants or comparable facilities, preferably with turnkey delivery experience. - Integration of buildings and civil structures, process plant engineering, hydraulic systems, electrical engineering, automation and supervisory control systems. - Construction within existing facilities and/or operationally sensitive sites. - Permitting management, HSE, construction sequencing and quality assurance. - Management of subcontractors, partners or international consortia under clear overall re-sponsibility. The mature project basis, clear functional objectives, high visibility and scope for optimisation make this project attractive to companies capable of assuming overall responsibility for complex, multi-discipline energy infrastructure.

  • Contact

    christine.knoop@stadtwerke-goerlitz.de
  • Type
    Planning
  • Location
    Görlitz
  • Main code
    Heating plant construction work
    45251200
  • 45213250Construction work for industrial buildings45231110Pipelaying construction work45232140District-heating mains construction work45310000Electrical installation work45350000Mechanical installations71320000Engineering design services

Similar active competitions

  • Stadtwerke Görlitz AG

    UNITED HEAT - Generalunternehmer für Detailed Engineering und Bauausführung - Klärwerk Nord

    Stadtwerke Görlitz AG sucht einen Generalunternehmer für Detailed Engineering und Bauausführung am Klärwerk Nord in Görlitz. Der Auftrag umfasst die Anbindung einer grenzüberschreitenden Leitung am Klärwerksstandort (WP12) sowie eine Schmutzwasserwärmepumpe (WP20). Erforderlich sind ein tragfähiges Konzept für Planung und Umsetzung im laufenden Klärwerksbetrieb, einschließlich BIM-/CAD-Methodik, Planungs- und Schnittstellenkoordination, Termin- und Beschaffungsstrategie, Inbetriebnahme sowie Risiko- und Qualitätsmanagement. Bewertet werden Preis (30 %) und Qualitätskonzepte (insgesamt 70 %), darunter Projektverständnis (20 %), Werk- und Ausführungsplanung (15 %), Termine, Beschaffung und Inbetriebnahme (15 %), Schnittstellen- und Risikomanagement (10 %) sowie Projektorganisation und Schlüsselpersonal (10 %).

    Competition with qualification
    Nov 16, 2026(8 days)
  • Würzburger Straßenbahn GmbH

    Anleggsmaskiner og utstyr

    Markterkundung! Keine Ausschreibung! Datenabfrage Wärmepumpenhersteller; Im Rahmen der Wärmewende ist am Auslauf der Kläranlage in Würzburg der Einsatz einer Wärmepumpenanlage mit rund 30 MWth vorgesehen. Die Wärmepumpenanlage nutzt das Wärmepotential des Klarwassers aus der Kläranlage aus der dritten, perspektivisch vierten. Reinigungsstufe.

    Die Stadtwerke Würzburg AG plant die Beschaffung einer Wärmepumpenanlage mit rund 30 MWth, die das Wärmepotenzial des Klarwassers aus der Kläranlage in Würzburg nutzen soll. Diese Vorinformation dient ausschließlich der Markterkundung, und interessierte Lieferanten werden gebeten, Daten abzufragen, um Input für ein mögliches zukünftiges Vergabeverfahren zu geben.

    Planning
    Dec 11, 2026(33 days)
  • Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH

    Anleggsmaskiner og utstyr

    Heat Pumps 50 KW el and 100 KW el

    Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH needs heat pumps for delivery in Main-Taunus-Kreis under a 9-month supply contract. The procurement covers five 50 kW electrical-input heat pumps and five 100 kW electrical-input heat pumps, each lot with two mandatory options; additional quantities of five units for each of Lots 3, 4 and 5 must also be offered, with acceptance conditional. Suppliers must document annual net turnover exceeding €300,000 in heat-pump supply for each of 2023, 2024 and 2025, and provide at least two heat-pump supply references from the previous three years.

    Competition
    Nov 10, 2026(2 days)