Search
  • Search


    Updating of Fingrid's type supports

    Fingrid Oyj

    Updating of Fingrid's type supports

    1. Competition notice published

      Aug 18, 2025 5:42 AMAugust 18, 2025 5:42 AM
    2. Supplier selection

      Nov 21, 2025 12:00 AMNovember 21, 2025 12:00 AM
    3. Contract signed

      Dec 17, 2025 12:00 AMDecember 17, 2025 12:00 AM
    4. Result notice published

      Feb 18, 9:34 AMFebruary 18, 2026 9:34 AM

    Brief

    Finland: Tenders/Fingrid Oyj/Updating of Fingrid's type supports

    Awarded

    The competition has ended and a winner has been selected.

    Qualification deadline
    Feb 17,Expired
    Award
    Abilibity to perform design work 29%
    Procedure
    With prequalificationTwo stages
    Agreement
    Buying servicesover 2 years

    Brief

    Fingrid Oyj har inngått en avtale med Dalekovod-Projekt, TLT-Building Oy og Despro Engineering Oy om å levere tjenester for oppdatering og oppgradering av design for standardstøtter, samt fornyelse av støttetester. Avtalen har en varighet på 24 måneder og en verdi på 45 000 euro. Seks leverandører deltok i konkurransen.

    Rådgivende ingeniørtjenester for bygg og anlegg

    Result

    TED
    • DALEKOVOD-PROJEKT d.o.o.
      Winner
    • Despro Engineering Oy
      Winner
    • TLT-Building Oy
      Winner
    • Number of bids
      6
    • Contract value
      €45,000

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Award Criteria

    • Description

      Estimation of costs

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      Abilibity to perform design work

      Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Fingrid Oyj

    From the notice

    • Fingrid Oyj has started updating and upgrading the design of standard supports. The update is necessary because the standards have been changed and the drawings are outdated. Fingrid Oyj is also renewing the support tests conducted between 2010 and 2016. The procurement of the design will be carried out in two stages. In the first stage, potential suppliers will be identified and their suitability assessed (prequalification). After this, official requests for Tender will be sent to the approved suppliers and they can submit their offers. This enquiry concerns prequalification of suppliers, where suppliers are asked to submit an application for prequalification (Stage 1). Results of this prequalification will be valid for all parts of design work. Due to the large number of support types, Fingrid has divided the work into several parts, each with its own Tendering process (Stage 2).

    • Contact

      Ritva Laineritva.laine@fingrid.fi
    • Type
      Result · Prequalification
    • Main code
      Public utilities
      65000000
    • 71323100Electrical power systems design services71327000Load-bearing structure design services71356300Technical support services

    Similar active competitions

    • Fingrid Oyj

      Elektrisk infrastruktur og veibelysning

      Overhead transmission line projects B-Qualification 2024

      Fingrid's overhead transmission line projects B-Qualification 2024.

      Qualification system
      Oct 30, 2026(1 day)
    • Fingrid Oyj

      Elektrisk infrastruktur og veibelysning

      Overhead transmission line projects A-Qualification 2024

      Fingrid's overhead transmission line projects A-Qualification 2024.

      Qualification system
      Oct 31, 2026(2 days)
    • Fingrid Oyj

      Rådgivende ingeniørtjenester for bygg og anlegg

      Voimajohtojen yleissuunnittelu, hyväksyntä 2026

      Fingrid Oyj etsii palveluntarjoajia voimajohtojen yleissuunnitteluun. Toimittajarekisteriin hyväksyntä perustuu taloudelliseen kelpoisuuteen, osaamiseen ja referensseihin.

      Qualification system
      Nov 30, 2027(100+ days)