Belgium: Tenders/Elia Asset/Virtual Substation - Data and Lifecycle Management Tool
  1. Competition notice published

    Aug 22, 2024 8:00 PMAugust 22, 2024 8:00 PM
  2. Qualification deadline

    Sep 27, 2024 10:00 AMSeptember 27, 2024 10:00 AM
  3. Invitation to submit tender

    Jan 9, 2025 11:00 PMJanuary 9, 2025 11:00 PM
  4. Tender submission deadline

    Comes with the invitation
  5. Contract start date

    Nov 1, 2025 12:00 AMNovember 1, 2025 12:00 AM
  6. Contract end date

    Oct 31, 2035 12:00 AMOctober 31, 2035 12:00 AM

Brief

Virtual Substation - Data and Lifecycle Management Tool

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Sep 27, 2024Expired
Procedure
With negotiationTwo stages
Agreement
Framework agreement
Estimated value
€7Muntil Oct 2035

Brief

The IEC61850 digital substation initiates a significant transition for users, specifically for large utilities with a high level of standardization. This transition can be a complex exercise, as users have developed their own engineering processes to suit the needs of copper-wired systems. As a result, many current IEC 61850 engineering implementations are private developments that are device-driven and labor-intensive. To address this challenge, IEC TC57 working group WG10 has identified a series of needs to evolve to a harmonized, market-supported, user-requirement-driven top-down process. To implement these requirements, WG10 has initiated the development of two technical reports: IEC 61850-90-30 (Function Modeling in SCL) and IEC 61850-7-6 ed2.0 (Basic Application Profiles in SCL). These reports define an SCL (System Configuration Language) extension namespace called IEC 61850-6-100 and document it’s use and application through multiple examples and use cases. While Elia has already digitalized some of the interaction between devices (IEC61850 station bus), it has the ambition to move forward towards the roll-out of full digital substations, converting electrical signals at their source to a digital data and using them in a digitalized system. To engineer these systems, Elia’s current engineering process and tools are not useable. Therefore, Elia is planning to implement a top-down process supported by the IEC61850 standard and the industry. Digitalization of substation protection and control functions comes with a new way of thinking. While current technology focuses on dataflow between Intelligent Electronic Devices (IEDs) considering only the interface of the IED and seeing the content of the IED as a black box, digital substation engineering requires the modeling of the end-to-end functions of a substation system. A substation is not seen any more as a grouping of different topological blocs (bays) that are engineered one by one but is in a digital world to be considered as a system that needs to be engineered and modelled as a whole. Besides the engineering tool itself, Elia is seeking to implement a data & lifecycle management system that will be embedded in this engineering ecosystem. The main goal is to implement a system that supports and guides the users throughout the full lifecycle of engineering the secondary systems of digital substations (concept, template and project), based on the IEC61850 standards. Key roles of the Product data/lifecycle management system (PLM/PDM) are: - Data/file library - Template library - Version management - XML data interpretation - XML data editing - Tracing of documents – dependency traceability - Data exchange - Document comparison - Change and issue management - User roles and management - API connectivity with other tools of the engineering ecosystem for data exchange - Workflow based lifecycle management The main drivers for this project are - Supporting technological evolution of the ELIA SPACS (substation protection, automation and control systems) for next (digital) generation and future generations (virtualization of protection and control applications) - Providing answers to important challenges of the current engineering processes - Realization of Elia’s goals on overall engineering efficiency and quality improvement Important criteria for the proposed solution are - Creating an engineering eco-system with individual interoperable and interchangeable tools - The solution requires a user experience that is intuitive, easy to understand and to learn - The solution needs to blend in in the IT landscape, and interact in a smooth way with other tools and eco-systems for the exchange of data. Elia has the ambition to use the output of this project for multiple SPACS generations to come, including the virtualization of protection and control applications.

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Elia Asset

From the notice

  • The IEC61850 digital substation initiates a significant transition for users, specifically for large utilities with a high level of standardization. This transition can be a complex exercise, as users have developed their own engineering processes to suit the needs of copper-wired systems. As a result, many current IEC 61850 engineering implementations are private developments that are device-driven and labor-intensive. To address this challenge, IEC TC57 working group WG10 has identified a series of needs to evolve to a harmonized, market-supported, user-requirement-driven top-down process. To implement these requirements, WG10 has initiated the development of two technical reports: IEC 61850-90-30 (Function Modeling in SCL) and IEC 61850-7-6 ed2.0 (Basic Application Profiles in SCL). These reports define an SCL (System Configuration Language) extension namespace called IEC 61850-6-100 and document it’s use and application through multiple examples and use cases. While Elia has already digitalized some of the interaction between devices (IEC61850 station bus), it has the ambition to move forward towards the roll-out of full digital substations, converting electrical signals at their source to a digital data and using them in a digitalized system. To engineer these systems, Elia’s current engineering process and tools are not useable. Therefore, Elia is planning to implement a top-down process supported by the IEC61850 standard and the industry. Digitalization of substation protection and control functions comes with a new way of thinking. While current technology focuses on dataflow between Intelligent Electronic Devices (IEDs) considering only the interface of the IED and seeing the content of the IED as a black box, digital substation engineering requires the modeling of the end-to-end functions of a substation system. A substation is not seen any more as a grouping of different topological blocs (bays) that are engineered one by one but is in a digital world to be considered as a system that needs to be engineered and modelled as a whole. Besides the engineering tool itself, Elia is seeking to implement a data & lifecycle management system that will be embedded in this engineering ecosystem. The main goal is to implement a system that supports and guides the users throughout the full lifecycle of engineering the secondary systems of digital substations (concept, template and project), based on the IEC61850 standards. Key roles of the Product data/lifecycle management system (PLM/PDM) are: - Data/file library - Template library - Version management - XML data interpretation - XML data editing - Tracing of documents – dependency traceability - Data exchange - Document comparison - Change and issue management - User roles and management - API connectivity with other tools of the engineering ecosystem for data exchange - Workflow based lifecycle management The main drivers for this project are - Supporting technological evolution of the ELIA SPACS (substation protection, automation and control systems) for next (digital) generation and future generations (virtualization of protection and control applications) - Providing answers to important challenges of the current engineering processes - Realization of Elia’s goals on overall engineering efficiency and quality improvement Important criteria for the proposed solution are - Creating an engineering eco-system with individual interoperable and interchangeable tools - The solution requires a user experience that is intuitive, easy to understand and to learn - The solution needs to blend in in the IT landscape, and interact in a smooth way with other tools and eco-systems for the exchange of data. Elia has the ambition to use the output of this project for multiple SPACS generations to come, including the virtualization of protection and control applications.

  • Contact

    bram.koster@elia.be
  • Type
    Competition · Framework agreement · Prequalification
  • Location
    Arr. de Bruxelles-Capitale/Arr. Brussel-Hoofdstad
  • Main code
    IT services: consulting, software development, Internet and support
    72000000

Similar active competitions

  • Elia Transmission Belgium

    Onshore Substations in EPCIC-FIM model

    In accordance with the latest Capex Plan, and the on-going energy transition, Elia intends to outsource multiple investment projects for onshore substations in Belgium that were previously realized in-house. The aim is to construct some substations in a EPCIC-FIM model. Meaning that the engineering, procurement (without noble materials/FIM), construction, installation and commissioning will be (partly) tendered in one contract. Only candidates that qualify in the prequalification phase of this EU procurement (see section 5.1.6) of this Qualification System will have access the tender phases.

    Qualification system
    Jun 11, 2027(100+ days)
  • Elia Asset

    Framework agreement - Busbar Protection (BBP) cubicles - 2029-2037

    Elia Asset needs a framework agreement for the design, engineering, manufacture, factory testing, packaging, transport, delivery and unloading of busbar protection (BBP) cubicles, including accessories, spare parts, after-sales service and related substation services, as well as a maintenance contract. The agreement covers delivery in Belgium and has an 8-year duration with a maximum total value of €18 million.

    Framework agreement with qualification
    Jan 14, 2027(57 days)
    €18,000,000
  • Alliander N.V.

    IT-drift og support

    Digitale aansturing van oefenomgevingen voor technische opleidingen

    Alliander N.V. heeft behoefte aan diensten voor het ontwerpen, realiseren, implementeren en beheren van een digitale oplossing voor de centrale aansturing van fysieke oefenomgevingen voor technische opleidingen. De oplossing moet het mogelijk maken om netconfiguraties en storingsscenario’s centraal te configureren, activeren, beheren en doorontwikkelen voor meerdere schakellokalen en meetvelden binnen Alliander. De raamovereenkomst heeft een maximale totale waarde van 3.040.000 EUR over een periode van 3 jaar.

    Framework agreement
    Nov 18, 2026(0 days)