    410119 Consultancy assistance regarding feasibility study of CCUS

    Fjernvarme Fyn Service A/S

    410119 Consultancy assistance regarding feasibility study of CCUS

    1. Contract signed

      Apr 20, 2023 12:00 AMApril 20, 2023 12:00 AM
    2. Result notice published

      Aug 25, 2023 8:00 AMAugust 25, 2023 8:00 AM

    Brief

    Denmark: Tenders/Fjernvarme Fyn Service A/S/410119 Consultancy assistance regarding feasibility study of CCUS

    Awarded

    The competition has ended and a winner has been selected.

    Qualification deadline
    Aug 24, 2023Expired
    Award
    Price 30% and 2 more
    Procedure
    With negotiationTwo stages
    Agreement
    Buying services

    Brief

    The objective of this study is the technical and economic feasibility of a carbon capture facility for the waste CHP plant owned and operated by Fjernvarme Fyn Affald A/S (FFA). FFA receives approximately 280.000 t/year of mixed waste and consequently the captured CO2 will be a mix of fossil and biogenic CO2. The major part of the biogenic CO2 is assumed to be utilized by Fortum for methanol production to the extent that this is feasible (to be investigated by Fortum in separate study) whereas not utlised CO2 shall be stored permanently. For further information please see the Tender Conditions and the Scope of feasibility study.

    Byggeteknisk konsulentvirksomhet

    Result

    TED
    • COWI A/S
      Winner
    • Number of bids
      3
    • Contract value
      Not stated

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Award Criteria

    • Description

      CV's

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      Project organization

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      Risk analysis and durabiltiy of the project

      Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Fjernvarme Fyn Service A/S

    From the notice

    • The objective of this study is the technical and economic feasibility of a carbon capture facility for the waste CHP plant owned and operated by Fjernvarme Fyn Affald A/S (FFA). FFA receives approximately 280.000 t/year of mixed waste and consequently the captured CO2 will be a mix of fossil and biogenic CO2. The major part of the biogenic CO2 is assumed to be utilized by Fortum for methanol production to the extent that this is feasible (to be investigated by Fortum in separate study) whereas not utlised CO2 shall be stored permanently. For further information please see the Tender Conditions and the Scope of feasibility study.

    • Contact

      Jette Køhlerjette.koehler@outlook.dk
    • Type
      Result · Prequalification
    • Main code
      Advisory and consultative engineering services
      71318000
    • 71600000Technical testing, analysis and consultancy services90492000Sewage treatment consultancy services90713000Environmental issues consultancy services

    Similar active competitions

    • Aalborg Universitet

      Laboratorie-, optisk- og presisjonsutstyr

      C-Tech test facility for Aalborg University (Esbjerg)

      Aalborg Universitet needs a C-Tech test facility for its Carbon Transformation & Energy Control Hub (C-TECH) project in Esbjerg, Sydjylland, with a maximum total value of 19,000,000 DKK. The facility should be a modular pilot and demonstration facility for carbon capture, utilization, and storage (CCUS) and Power to X (PtX) technologies, consisting of an integrated setup of four 20-foot containers housing electrolysis (hydrogen production), CO2 capture, methanol synthesis, and a supply container. The project aims to accelerate the development and demonstration of CCUS and Power to X technologies, contribute to competence development, and foster collaboration with industry partners. Tenders will be evaluated based on price (40%) and quality (60%).

      Competition
      Jan 7, 2027(70 days)
      DKK 19,000,000
    • Brande Fjernvarme A.m.b.a.

      Varmepumper og energianlegg

      Levering og etablering af 15 MW fliskedelanlæg

      Brande Fjernvarme A.m.b.a. udbyder en totalentreprise til en maksimal samlet værdi på 140 mio. DKK for projektering, levering, opførelse, idriftsættelse og aflevering af et nøglefærdigt flisfyret kedelanlæg på ca. 15 MW i Brande. Anlægget skal omfatte kedelbygning, brændselslager, røggasrensning og -kondensering, fjernvarmevekslere samt el-, PLC- og SRO-systemer og levere varme til fjernvarmenettet og hedtvand på mindst 180 °C til en industriel aftager. Entreprisen inkluderer 3 års service med option på service frem til 10 år efter aflevering; anlægget skal forberedes til en absorptionsvarmepumpe, som ikke er omfattet. Konkurrencen gennemføres med prækvalifikation og forhandling, hvor højst fem ansøgere udvælges, og forhandlingen kan foregå i flere faser. Tilbuddene vurderes på teknik, funktion og kvalitet (50 %), organisering og tidsplan (20 %) samt pris (30 %). Ansøgere skal dokumentere mindst én reference fra de seneste 8 år på et biomassefyret kedelanlæg på mindst 10 MW pr. kedel, leveret som total- eller samlet maskinentreprise med ansøger eller en støttende enhed som hovedentreprenør eller hovedleverandør.

      Competition with qualification
      Nov 23, 2026(25 days)
      DKK 140,000,000
    • Gas Storage Denmark A/S

      Rådgivende ingeniørtjenester for bygg og anlegg

      Combined Service for Methane Emissions Measurements and Reporting Basis - 26/15049

      Gas Storage Denmark A/S needs methane-emissions measurement and reporting services for its two underground natural-gas storage facilities in Denmark, located in West and South Zealand and North Jutland, with a maximum total contract value of DKK 2.8 million. The services must support measurement, quantification, monitoring, reporting and verification under the EU Methane Regulation. Tenders are evaluated on price (60%), relevant references (20%) and organization (20%); bidders must provide two comparable references, particularly assignments involving methane measurement and quantification, facility operations and reporting for executive or political decision-making. The proposed team should include qualified and available personnel for each work package, with clear responsibilities, backup capacity and plans for continuity and collaboration with Energinet.

      Competition
      Nov 11, 2026(13 days)
      DKK 2,800,000