Ireland: Tenders/Electricity Supply Board ( ESB )/CON815: Qualification System for Distribution and Transmission Electrical Substation Works. Reference Number: Etender ID No: 114371.
  1. Competition notice published

    Nov 19, 2024 9:25 AMNovember 19, 2024 9:25 AM
  2. Tender submission deadline

    Nov 19, 2024 10:25 AMNovember 19, 2024 10:25 AM

Brief

CON815: Qualification System for Distribution and Transmission Electrical Substation Works. Reference Number: Etender ID No: 114371.

Deadline
Dec 17, 2027393 days left
Agreement
Construction work

Brief

Qualification System for Distribution and Transmission Electrical Substation Works.

Elektrisk infrastruktur og veibelysning

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Electricity Supply Board ( ESB )

From the notice

  • Qualification System for Distribution and Transmission Electrical Substation Works.

  • Contact

    Sinead Verekersinead.vereker@esb.ie
  • Type
    Competition
  • Location
    Dublin
  • Main code
    Transformer substation
    45232221
  • 45317200Electrical installation work of transformers45317300Electrical installation work of electrical distribution apparatus50532400Repair and maintenance services of electrical distribution equipment51110000Installation services of electrical equipment51112000Installation services of electricity distribution and control equipment

Similar active competitions

  • Electricity Supply Board ( ESB )

    Elektrisk infrastruktur og veibelysning

    CON1199 - Qualification System for Electrical Distribution Substation Works

    Electricity Supply Board (ESB) needs expressions of interest for a Qualification System for the subsequent procurement of engineering, civil, design, equipment and material supply, operation, maintenance, and construction services related to electrical power distribution assets, mainly within substations but also power distribution cables, ring main units, mini-pillars, and other associated assets throughout the distribution network, up to 110 kV voltage level. The works will be located in the Republic of Ireland.

    Qualification system
    Jul 2, 2029(100+ days)
  • Electricity Supply Board ( ESB )

    CON1140 Qualification System for the at scale EPC delivery of 110 kV, 220 kV and 400 kV HV Substations and Substation Programmes

    ESB proposes to establish a qualification system under a negotiated procedure for the at scale EPC delivery of 110 kV, 220 kV and 400 kV HV Substations and Substation Programmes. It is envisaged that a significant number of DSO and TSO GIS Substations will be constructed during the period 2026 - 2035 and will be delivered via this procurement process as outlined in Section A Information Memorandum, attached to this publication. Substations procured under this Qualification System will include for a full end to end scope of delivery which may include in some cases site acquisition and achievement of planning permission on behalf of the Contracting Entity. The scope of substation projects under this Qualification System may include a requirement for the inclusion of additional technologies including but not limited to STATCOMS and series compensators. The First Procurement under the Qualification System is envisaged to be: • Framework for PR6 Capacity at scale EPC delivery of 110 kV and/or 110 kV to /38 kV/MV Substations and Substation Programmes. Economic Operators who wish to participate in this qualification system process should submit a response as set out in the Section A Information Memorandum document. While applications may be made to join the Qualification System at any time, those interested in being considered for the Initial Framework (the “First Procurement”) under this Qualification System should submit a completed QSQ response on or before 1200 hrs (local time) on Friday 27th June 2025 (the “First Procurement Closing Date”).

    Qualification system
    Jun 16, 2028(100+ days)
  • Electricity Supply Board ( ESB )

    Elektrisitet og energiforvaltning

    Commissioning and Engineering-related Services Qualification System

    Commissioning and Engineering-related Services Qualification System

    Qualification system
    Jun 4, 2027(100+ days)