    Finland: Tenders/Fortum Power and Heat Oy/FORTUM HEATING AND COOLING FINLAND: MAJOR OVERHAUL SERVICE FOR SO2 GAS TURBINE 2025
    1. Competition notice published

      Mar 7, 2024 7:24 AMMarch 7, 2024 7:24 AM
    2. Qualification deadline

      Mar 29, 2024 10:00 AMMarch 29, 2024 10:00 AM
    3. Tender submission deadline

      Comes with the invitation

    Brief

    FORTUM HEATING AND COOLING FINLAND: MAJOR OVERHAUL SERVICE FOR SO2 GAS TURBINE 2025

    Published deadline passed

    The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

    Qualification deadline
    Mar 29, 2024Expired
    Procedure
    Competitive dialogueTwo stages
    Agreement
    Framework agreementover 3 months

    Brief

    This public procurement project is regarding major overhaul of Suomenoja power plant SO2 Gas Turbine (model: AE94.2+ (6) s/n G156TG class Heavy-duty gas turbine) built in 2009 (Address: Hylkeenpyytäjäntie 4, 02270 Espoo, Finland). The purchase includes both works and spare parts regarding the overhaul. The Purchaser is planning to execute major overhaul for the unit during summer 2025. This invitation letter is a call for potential suppliers to participate to the tendering regarding overhaul scope.

    Register interest

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Award Criteria

    • Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Fortum Power and Heat Oy

    From the notice

    • This public procurement project is regarding major overhaul of Suomenoja power plant SO2 Gas Turbine (model: AE94.2+ (6) s/n G156TG class Heavy-duty gas turbine) built in 2009 (Address: Hylkeenpyytäjäntie 4, 02270 Espoo, Finland). The purchase includes both works and spare parts regarding the overhaul. The Purchaser is planning to execute major overhaul for the unit during summer 2025. This invitation letter is a call for potential suppliers to participate to the tendering regarding overhaul scope.

    • Contact

      esa.parkko@fortum.com
    • Type
      Competition · Framework agreement · Prequalification
    • Main code
      Turbine installations
      42112000

    Similar active competitions

    • Bord na Móna PLC

      Oppføring av bygninger

      SC 07/25 - Open Cycle Gas Turbine (OCGT) and Combined Cycle Gas Turbine (CCGT) Qualification System

      Bord na Móna PLC in Ireland is establishing a Qualification System for the provision of Open Cycle Gas Turbine (OCGT) and Combined Cycle Gas Turbine (CCGT) works. This system is of indefinite duration, but is anticipated to apply for 10 years with an option to extend. The procurement covers Lot 1 – OCGT Supply OEM and LTSA, Lot 2 – OCGT Balance of Plant Constructor, Lot 3 – OCGT Engineering, Procurement and Construction (EPC) LTSA, and Lot 4 – CCGT Engineering, Procurement and Construction (EPC) + LTSA.

      Qualification system
      Oct 6, 2029(100+ days)
    • Fortum Power and Heat Oy

      Elektrisitet og energiforvaltning

      Esivalinta - Espoon, Kauniaisten ja Kirkkonummen alueen kaukolämpö- ja kaukojäähdytysverkoston rakentamisen vuosiurakoinnin raamisopimuskilpailutus

      Fortum Power and Heat Oy hakee raamisopimuskumppaneita Espoon, Kauniaisten ja Kirkkonummen kaukolämpö- ja kaukojäähdytysverkoston vuotuisiin korjaus-, saneeraus- ja uudisrakennustöihin. Urakkaan sisältyy rakennus-, putkiasennus- ja eristystöitä, ja työt sijoittuvat Fortumin verkkoalueille Espoossa, Kauniaisissa ja Kirkkonummella. Tarjouksia arvioidaan hinnan ja laadun perusteella; tarkemmat arviointiperusteet ilmoitetaan tarjouspyyntövaiheessa. Vuoden 2023 vastaavan kilpailutuksen voittivat Maalinja Oy ja Maarakennusliike Pusku Oy.

      Framework agreement with qualification
      Nov 11, 2026(12 days)
    • UAB Panevėžio regiono atliekų tvarkymo centras (PV)

      Rørlegger- og sanitærarbeid

      Kogeneracinės jėgainės MWM TCG 2016 V12C techninio aptarnavimo ir priežiūros paslaugos

      UAB Panevėžio regiono atliekų tvarkymo centras (PV) reikalingos kogeneracinės biodujų jėgainės MWM TCG 2016 V12C remonto ir techninio aptarnavimo paslaugos (pagal gamintojo nustatytus reikalavimus E10, E30, E40, E60, E70) Panevėžio apskrityje, 25 mėnesių laikotarpiui.

      Competition
      Nov 16, 2026(17 days)