Energinet Eltransmission A/S has cancelled a tender for a framework agreement to purchase complete glass insulator strings for powerlines and substations in Denmark. The agreement was intended to last for 4 years with two 2-year extension options, with an estimated total maximum value of 30,442,953 EUR. The procurement was divided into two lots: Lot 1 for powerlines with an expected consumption of 10,000,000 EUR (maximum 24,000,000 EUR) and Lot 2 for substations with an expected consumption of 2,684,563.75 EUR (maximum 6,442,953.00 EUR). The evaluation criteria included price (30%), quality (50%) focusing on high-performing, well-designed, and robust solutions with documented operational experience, visual impact, handling instructions, labeling, storage descriptions, and corona extinction voltage reports, and delivery time (20%).
Diverse konstruksjonsmateriell
Result
- Reason for cancellationAnnet
- 0Number of bids
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Qualification requirements
Description
Egenkapital fra siste årsrapport må på tidspunktet for innlevering av tilbud være minst 2 500 000 EUR.
Documentation Requirement
Søkeren må bekrefte økonomisk evne i ESPD del IV.B med informasjon fra siste årsrapport angående egenkapital (total egenkapital inkl. aksjekapital, reserver, revaluering, tilbakeholdt overskudd etc.).
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Egenkapitalandelen fra siste årsrapport må på tidspunktet for prekvalifisering være minst 20 %. Hvis egenkapitalandelen er mellom 15 % og 20 %, kan søkeren kvalifisere hvis egenkapitalen overstiger 7 500 000 EUR.
Documentation Requirement
Søkeren må bekrefte økonomisk evne i ESPD del IV.B med informasjon fra siste årsrapport angående egenkapitalandel (egenkapital/totale eiendeler). Dette må oppgis med to desimaler.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Søkeren skal levere tre (3) til fem (5) mest sammenlignbare og relevante referanser utført de siste fem (5) årene. Med «utført de siste [X] årene» menes at referansen ikke må være fullført før datoen som nås når man teller fem (5) år tilbake fra innleveringsdatoen for prekvalifisering. Referanser eldre enn dette vil ikke bli tatt i betraktning. Referanser som ennå ikke er fullført, kan inkluderes som en del av søknaden, men søkeren må beskrive de delene som ennå ikke er levert, og dette kan påvirke evalueringen av søkeren, jf. avsnitt 2.3. Referansene skal inkludere: - Mengde: Sammenlignbar med mengdene spesifisert i Vedlegg 3A – Prisliste transformatorstasjoner og Vedlegg 3B – Prisliste kraftledninger. - Kontraktsverdi: Omtrent tilsvarende verdien av den nåværende kontrakten, der det er mulig. - Spenningsnivå: Leveranser knyttet til overføringssystemer innenfor området 132 kV til 450 kV. - Værforhold: Referanseprosjektene skal være lokalisert i områder med vær- og miljøforhold som er sammenlignbare med de i Danmark. Beskriv relevante forhold der det er aktuelt. - Land: Spesifiser landet der referanseprosjektet ble utført. - Kundereferanse: Navn på mottaker/kunde, inkludert navn på kontaktperson og deres kontaktdetaljer (e-postadresse og telefonnummer). - Prosjektets tidslinje: Dato for kontraktsinngåelse/oppstart og dato for endelig levering (dag, måned, år). Minimumskrav for Lot 1 og Lot 2: 132 kV er minimumskravet for spenningsnivå.
Documentation Requirement
Søkeren skal fylle ut referanser i ESPD del IV.C.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Leverandøren skal levere produsentens instruksjoner for håndtering, lagring, lossing og utpakking av produktene.
Documentation Requirement
Ikke spesifisert.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Leverandøren skal beskrive om produktene kan håndteres manuelt eller om løfteutstyr eller andre tekniske hjelpemidler er nødvendig under lossing, utpakking og håndtering. Beskrivelsen skal inkludere informasjon om produktvekt, emballasjekonfigurasjon og eventuelle spesifikke håndteringskrav.
Documentation Requirement
Ikke spesifisert.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Leverandøren skal spesifisere eventuelt personlig verneutstyr (PVU) anbefalt eller påkrevd av produsenten for sikker håndtering av produktene. Dette skal inkludere, men ikke være begrenset til, beskyttelse mot skarpe kanter, klemmefarer, kutt og andre risikoer forbundet med håndtering av produktene.
Documentation Requirement
Ikke spesifisert.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Leverandøren skal sikre at alle produkter levert under rammeavtalen kan håndteres trygt i samsvar med gjeldende krav til arbeidsmiljø og sikkerhet.
Documentation Requirement
Ikke spesifisert.
Source
No source found in the documents. Check the requirement against the tender documents.
Award Criteria
Description
The tenderer must include documentation of fulfillment and a list of reservations to appendix 2A and 2B. The clarification should be explicit and with explanation as to why the clarification is made. In the evaluation of 'Solution description', Energinet will emphasize the following: Considering the scope and content of the tendered contract the Contracting Authority will focus on to what extend the submitted ensures delivery of high performing, well designed and robust. Beside Specifications in the technical requirements, the elements listed below are of particular importance: Visual impact from the insulator string design (Drawings of each string type), The proposed complete string design shall be based on proven design solutions with documented long-term operational experience. Examples of documented results from design tests, type tests, and sample tests. Document with handling instructions. Example of labeling of all parts. Description of outside storage in all weather conditions. Report demonstrating the strings meet the requirement for a minimum corona extinction voltage of 300 kV, based on the voltage gradient method. It will impact the evaluation positively to the extend the technical description/solution including supporting documents are detailed, thorough and precise. An overall evaluation will be made of the solution description.
Evaluation Method
In the evaluation of 'Solution description', Energinet will emphasize the following: Considering the scope and content of the tendered contract the Contracting Authority will focus on to what extend the submitted ensures delivery of high performing, well designed and robust. Beside Specifications in the technical requirements, the elements listed below are of particular importance:
- Visual impact from the insulator string design (Drawings of each string type)
- The proposed complete string design shall be based on proven design solutions with documented long-term operational experience.
- Examples of documented results from design tests, type tests, and sample tests.
- Document with handling instructions
- Example of labeling of all parts
- Description of outside storage in all weather conditions.
- Report demonstrating the strings meet the requirement for a minimum corona extinction voltage of 300 kV, based on the voltage gradient method.
It will impact the evaluation positively to the extend the technical description/solution including supporting documents are detailed, thorough and precise. An overall evaluation will be made of the solution description.
Source
No source found in the documents. Check the weight against the tender documents.
Description
Prices must be stated in the attached Price List and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR. When evaluating 'Price', the Contracting Authority will evaluate the total cost (for evaluation purpose), cf. the Price List.
Evaluation Method
When evaluating 'Price', the Contracting Authority will evaluate the total cost (for evaluation purpose), cf. the Price List.
Source
No source found in the documents. Check the weight against the tender documents.
Description
Delivery time must be stated in the attached tender list. When evaluating 'Delivery time', Energinet will evaluate the delivery time in the tender list. The Tenderer shall state the lead time, expressed in calendar weeks, for a typical order consisting of: 300 suspension strings; and 30 tension strings. The stated lead time shall be used for evaluation purposes.
Evaluation Method
Lead time will be evaluated using a linear scoring model, where:
- 20 weeks = 10 points
- 40 weeks = 5 points
- 60 weeks = 0 points
Scores for lead times between 20 and 60 weeks will be calculated by linear interpolation. Lead times shorter than 20 weeks will receive the maximum score of 10 points, while lead times longer than 60 weeks will receive 0 points.
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Energinet Eltransmission A/S
From the notice
The Contracting Authority wants to purchase complete glass insulator strings. For further details regarding the purchase, reference is made to the tender documents: Ap-pendix 2A scope of works for powerlines and 2B Scope of work for substations. The tendered framework agreement has a duration of four (4) years. The framework agree-ment can be extended two (2) times for two (2) years each time. The framework agreement is divided into the following lots: • Lot 1: Complete glass insulator strings for powerlines. Expected consumption to be: EUR 10.000.000. Maximum value is EUR 24.000.000 • Lot 2: Complete glass insulator strings for substations. Expected consumption to be: EUR: 2.684.563,75. Maximum value is EUR 6.442.953,00 euro. Tenders can be submitted for all Lots. Tenderers are not required to submit a tender for both lots Offers can be submitted for all partial agreements The estimated consumption during the term of the framework agreement is expected to amount to be divided into lots. The consumption figures are estimates only and are consequently not binding for the Contract-ing Authority. During the specified period, the Contracting Authority has the right to purchase the services and/or goods comprised by the framework agreement from the selected tenderer but is not obligated to do so cf. the framework sec. 1.3.Main features of the procedureThe tenders submitted must be valid for a period of six 6 months as from the specified time limit for the submission of tenders. If the tenderer during the negotiation phase, prepares and submits revised tenders, such tenders must also be valid for the period of [6] months from the specified time limit for these revised tenders.
Contact
Anja LorenzenANL@energinet.dk- Result · Framework agreement · PrequalificationType
- 44111500Main codeInsulators and insulating fittings