    Framework agreement regarding Third-Party Verification and Certification of the Danish Hydrogen Backbone

    Energinet Brint A/S

    Framework agreement regarding Third-Party Verification and Certification of the Danish Hydrogen Backbone

    1. Tender submission deadline

      Jan 20, 2025 11:00 AMJanuary 20, 2025 11:00 AM
    2. Competition notice published

      Sep 8, 2025 6:12 AMSeptember 8, 2025 6:12 AM
    3. Result notice published

      Sep 25, 2025 8:10 AMSeptember 25, 2025 8:10 AM

    Brief

    Denmark: Tenders/Energinet Brint A/S/Framework agreement regarding Third-Party Verification and Certification of the Danish Hydrogen Backbone

    Cancelled

    The competition has been cancelled.

    Qualification deadline
    Sep 24, 2025Expired
    Award
    CV and Organization 30% and 2 more
    Procedure
    With negotiationTwo stages
    Agreement
    Framework agreement
    Estimated value
    €13Mover 5 years

    Brief

    Energinet Brint A/S har avlyst konkurransen om en rammeavtale for tredjepartsverifisering og sertifisering av den danske hydrogenryggraden (DHB-1-prosjektet) på grunn av endrede behov. Rammeavtalen hadde en estimert totalverdi på 13 millioner euro og skulle vare i 5 år, med opsjon på forlengelse i 2+1 år. Tjenestene skulle dekke alle faser av DHB-1-prosjektet, fra detaljert design til testing og igangkjøring, med formål om å ta hydrogenoverføringsanlegget i drift. Det ble stilt krav om erfaring med hydrogenprosjekter eller tilsvarende teknologier, samt kompetanse innen relevante standarder og dansk lovgivning. Én leverandør deltok i konkurransen.

    Arkitekttjenester

    Result

    TED
    • Reason for cancellation
      Besluttning av oppdragsgiveren på grunn av behovsendring
    • Number of bids
      1

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Qualification requirements

    • Description

      Equity from the latest annual report must, at the time of prequalification, be at least 20,000,000 EUR.

      Documentation Requirement

      The applicant must confirm the economic ability in the ESPD part IV.B with information from the latest annual report regarding equity. If the applicant relies on the capacities of other entities (e.g., an affiliated company or a subcontractor) or the applicant is a group of economic operators (e.g., a consortium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities. It is the sole responsibility of the applicant to secure that the minimum requirements are reached based on consolidation when the applicant is relying on the capacity of other entities or when the applicant is a group of economic operators.

      Source

      No source found in the documents. Check the requirement against the tender documents.

    • Description

      Equity ratio (equity/total assets) from the latest annual report must, at the time of prequalification, be at least 15 pct. This must be stated with two decimals.

      Documentation Requirement

      The applicant must confirm the economic ability in the ESPD part IV.B with information from the latest annual report regarding equity ratio. If the applicant relies on the capacities of other entities (e.g., an affiliated company or a subcontractor) or the applicant is a group of economic operators (e.g., a consortium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities. It is the sole responsibility of the applicant to secure that the minimum requirements are reached based on consolidation when the applicant is relying on the capacity of other entities or when the applicant is a group of economic operators.

      Source

      No source found in the documents. Check the requirement against the tender documents.

    Award Criteria

    • Description

      The tenderer must enclose a detailed ‘Solution Description’ for the contract tendered in relation to all elements as requested in Enclosure D – Guideline on content of the “Solution Description”. Responses in relation to the ‘Solution Description’ should be a general description of the interpretation of the Tenderer to the requested Scope of Services and contain as a minimum all information requested in Enclosure D. Reponses shall be dis-cussed as a part of the negotiation and clarification meet-ing(s). The response can be otherwise unconstrained but must be a maximum of twenty (20) A4 pages, including 2,400 characters spaced per A4 page or a total number of characters of 48,000 distributed over the twenty (20) pages. If the scope of the response exceeds the maximum number of pages, only the first twenty (20) pages will be considered in the assessment, or if the number of characters exceeds 48,000 characters, then only the material within this impact limit will be evaluated. Front page and table of contents do not count.

      Evaluation Method

      The evaluation of the “Solution description” will depend upon the content and level of detail of the proposed solution description in relation to fulfilment of the Scope of Services. It will be evaluated highly positively if: The description demonstrates a high level of ability to identify relevant activities and challenges in relation to the topics raised in Enclosure D. The description proposes appropriate and specific methods, tools and processes for managing verification and certification services. An overall evaluation of this sub criterion will be made. For the sub‐criteria “Solution description” it is a minimum re-quirement that the tenderers reach a minimum score of four (4), cf. section 3.7.1.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      For the evaluation of this sub-criteria the following should be enclosed: One (1) CV for the Project Manager, One (1) CV for the discipline lead for the WP “Detailed design”, One (1) CV for the discipline lead for the WP “Fabrication and manufacture”, One (1) CV for the discipline lead for the WP “Installation and construction”, One (1) CV for the discipline lead for the WP “Testing and pre-commissioning”. It is of high importance that the categories 1, 2 and 3 shall be represented within the requested amount of five (5) CVs. A CV is not to be reused, and the Client therefore requests five (5) independent CVs. All submitted CVs shall be numbered from 1-5 and this number must be transferred as a reference in Enclosure C – Price List (doc. 25/06071-9). No CVs shall be submitted in categories 4 and 5. The submitted CVs demonstrated will be recognized as the key personnel offered to the Client for the period of the framework agreement and Agreement under the Framework Agreement. The CVs should include a detailed description of experience and competences of relevance to the tendered assignment considering the position for which the key person is proposed (e.g. experience within that position, experience with similar assignments etc.). Max. number of pages per CV is limited to three (3) pages, if the CV contains more than three (3) pages only the first three (3) pages will be evaluated. The tenderer should enclose a detailed description of the project specific organizational structure which will be allocated to major phases of the assignment (detailed design, fabrication & manufacture, construction, installation and testing), including: Level of involvement of the key personnel and how the competences of the key personnel will be used for the specific assignment, How the key personnel complement each other within the organization structure, How external interfaces are administrated, including how subcontractors (if any) will be involved and administrated. The availability and structure of additional expert or ‘second line’ support, How lines of communication internally and externally will be handled appropriately and efficiently. The description “Organization” must not exceed six (6) A4 pages. If the scope of the response goes beyond the maximum number, only the first six (6) pages will be considered in the assessment of each sub-agreement. The front page and table of contents do not count. Further to the detailed description of “Organization”, the tenderer should include a visual chart illustrating the organizational structure. This is not a part of the six (6) pages.

      Evaluation Method

      The evaluation of “CVs” will be based on the demonstrated com-petences and experiences in the included CVs with respect to the tendered assignment and the specific role of the key person, including to which degree the individual key personnel will be involved in the fulfillment of the assignment and how they complement each other. It will be evaluated highly positively if the CV demonstrates: Experience with hydrogen projects or equivalent using emerging technologies, Experience, competencies and expertise regarding re-view of project documentation within all elements of pipeline, plant and process equipment, The ability to work under DNV-SE-0474, DNV-SE-0471, DNV-SE-0479 and DNV-SE-0656 (alternatives must demonstrate equivalence), Experience and familiarity with working within Danish legislation and working practices, Experience with Codes, Standards, Guidelines and In-dustry Practices of relevancy with respect to gas transport, storage and processing, including (for exam-ple) ATEX, LVD, PED, fire-safety. The evaluation of “Organization” will be based on whether the proposed organizational structure is operationally efficient and has clear lines of communication taking into consideration the scope of the assignment. It will be evaluated highly positively if the description of organization demonstrates: An organizational structure, which demonstrates the ability to provide the requested verification and certifi-cation services throughout the period of contract, An active, accredited, integrated risk, safety and quality management system, Accreditation to as many of the relevant directives, ex-ecutive orders, codes, standards and guidelines, as pos-sible e.g. Accreditation to: PED module G (EU), Danish Executive Order 99 (DK) and/or Danish Executive Order 498 (DK), Demonstrated ‘Organizational Readiness’ through ac-tive participation with research or joint-industry pro-jects related to this assignment. An overall evaluation will be made of this sub-criterion. For all other sub‐criteria than “Price” it is a minimum require-ment that the tenderers reach a minimum score of four (4) to be com-pliant, cf. section 3.7.1

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      Prices must be stated in the attached Enclosure E - Price List (Doc. 25/06071-9) and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR.

      Evaluation Method

      When evaluating 'Price', the Contracting Authority will evaluate the total weighted hourly rates (for evaluation purposes), cf. the Price List item 500.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      The tenderer must as part of the sub-criterion “Contract Terms” include the following (if applicable): A list of proposed deviations to the attached contractual terms, cf. legal documents: the Framework Agreement (doc.no. 25/06071-7), the Agreement under the Framework Agreement (doc.no. 25/06071-13) and the General terms and Conditions for Verification and Certification Services (doc.no. 25/06071-13), which shall be stated in the “Clarification List” under the sheet “Legal”. The proposed deviations should be explicit and with explanation as to why they are made.

      Evaluation Method

      The tendered assignment must be performed on the basis of the attached Contract Terms. With the exception of the following sections in: The legal conditions stated in the Framework Agreement (doc.no. 25/06071-7) - Clause 2 (Documents forming the Agreement), Clause 14 (Disputes and Applicable Law). The legal conditions stated in the Agreement under the Framework Agreement (doc.no. 25/06071-13) - Clause 2 (Documents forming the Agreement). The legal conditions stated in the General terms and Conditions for Verification and Certification Services (doc.no. 25/06071-13) - Sub-clause 6.13 (Invoicing), Sub-clause 6.14 and 6.15 (Final date for payment and late payment), Clause 25 (Disputes and applicable law). which is not part of the evaluation of “Contract terms”, as these terms are mandatory, and it is therefore not possible for the tenderer to have deviations to these sections. It is contrary possible for the tenderer to make explicit and well explained deviations to the other sections. Any deviation will be included in the evaluation of the sub criterion "Contract terms" and it is noted that any deviations may lead to a reduction to the score depending on the content, clarity and consequence. In this regard it is explicitly noted that deviations which intend to limit liability and shift the financial risk in favor of the tenderer will be of particular importance in the evaluation. No deviations, and thereby absolute fulfillment of the contract terms, will result in a maximum score of ten (10). For all other sub‐criteria than “Price” it is a minimum requirement that the tenderers reach a minimum score of four (4) to be compliant, cf. section 3.7.1. An overall evaluation will be made of this sub-criterion.

      Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Energinet Brint A/S

    From the notice

    • The scope of services for the framework agreement includes all phases of the DHB-1 project from detailed design to testing and commissioning for the purpose of taking the hydrogen transmission asset into operation. Major project phases include, for example, detailed design; fabrication and manufacture of system components; installation, construction and testing of the installed components; including sufficient documentation and due diligence to meet all necessary internal guidelines, and external governance such as directives, executive orders, standards, codes and established industry guidelines. These directives and the like form the basis of the ‘Project Compliance Plan. The Contracting Authority wants to purchase verification and certification services from an independent, third-party agency in order to satisfy those verification and certification requirements laid down under the compliance plan. The full scope of services of the design & installation contractors, including a full description of all known project constraints against which the Project shall be Verified or Certified, is included in this document package. For further details regarding the purchase, reference is made to the tender documents. The tendered framework agreement has a duration of five (5) years. The framework agreement can be extended with two (2) years + one (1) years. Subsequent contracts under the framework agreement will be awarded directly to the supplier who submitted the most economically advantageous tender, see section 4.1. The consumption figures are estimates only and are consequently not binding for the Contracting Authority. During the specified period, the Contracting Authority has the right to purchase the services and/or goods comprised by the framework agreement from the selected tenderer, but is not obligated to do so, cf. the framework sec. 1.3.Main features of the procedureThe tenders submitted must be valid for a period of six (6) months as from the specified time limit for the submission of tenders. If the tenderer during the negotiation phase, prepares and submits revised tenders, such tenders must also be valid for the period of six (6) months from the specified time limit for these revised tenders.

    • Contact

      Procurement - Sprocurement@energinet.dk
    • Type
      Result · Framework agreement · Prequalification
    • Main code
      Architectural, construction, engineering and inspection services
      71000000
    • 71631000Technical inspection services79132000Certification services

    Similar active competitions

    • Energinet Eltransmission A/S

      Diverse konstruksjonsmateriell

      Re-tendering - Framework agreement: Purchase of fittings for glass insulator strings 26/17723

      Energinet Eltransmission A/S needs to purchase complete glass insulator strings through a framework agreement over 4 years, with two options for extension of 2 years each, for a total potential duration of 8 years. The maximum total value of the agreement is 30,442,953 EUR. The procurement is divided into two lots: Lot 1 for complete glass insulator strings for powerlines, with an expected consumption of 10,000,000 EUR and a maximum value of 24,000,000 EUR; and Lot 2 for complete glass insulator strings for substations, with an expected consumption of 2,684,563.75 EUR and a maximum value of 6,442,953.00 EUR. Tenders can be submitted for one or both lots. The award criteria are Quality (41.6667%), Delivery time (16.6667% + 16.6667% = 33.3334%), and Price (25%). Qualification requirements include an equity of at least 2,500,000 EUR and an equity ratio of at least 20% (or 15-20% if equity exceeds 7,500,000 EUR) for Lot 1. Additionally, applicants must provide three to five comparable and relevant references from the past five years, with at least one reference demonstrating the supply of glass insulators for a transmission network with a voltage level of at least 132 kV.

      Framework agreement with qualification
      Nov 2, 2026(4 days)
      €30,442,953
    • Ministry of Foreign Affairs of Denmark

      Markeds- og opinionsundersøkelser

      Consultancy framework agreement for formulation, appraisal and review of Danish development cooperation programmes and projects

      The Ministry of Foreign Affairs of Denmark seeks a multi-supplier framework agreement for 2 years, with a maximum total value of DKK 250 million, to provide consultancy services for the formulation, appraisal and review of Denmark’s bilateral development cooperation programmes and projects, funded by official development assistance. The work is divided into two lots: climate, environment, private sector and financing; and governance, fragility and migration. Assignments will be commissioned individually and may cover programme or project formulation, appraisal as a quality-assurance milestone, and reviews during implementation; evaluations and several other service areas are excluded. The framework is intended to provide timely access to specialists and improve service quality, and five suppliers will be selected for each lot. Award criteria are thematic specialists (48%), quality assurance (16%), organisational and management approach (12%), mobilisation of specialists (12%) and financial management specialists (12%). Applicants must document at least DKK 25 million in relevant official-development-assistance consultancy turnover across the three most recent available financial years, and provide up to 10 relevant references per lot for services performed in the preceding five years.

      Framework agreement with qualification
      Nov 24, 2026(26 days)
      DKK 250,000,000
    • EnBW Energie Baden-Württemberg AG

      Rock Dumping Services

      1. Introduction The Scope of Work (SoW) defines the requirements, methodologies, and deliverables for the provision of Rock Dumping Services, including the design, supply, installation, and verification of rock berms for the protection and stabilization of subsea cables, CPS, Foundations, and related offshore infrastructure. The services are to be executed at the designated offshore wind farm locations in the German North Sea sector, Baltic Sea Sector or any other european offshore wind farm location. 2. Objectives Protection of Subsea Assets: To protect subsea cables, cable protection systems (CPS), and foundations from environmental and operational risks, such as scouring, freespan, and mechanical damage. Stabilization: To ensure long-term stability and integrity of subsea infrastructure by installing engineered rock berms. Compliance: To execute all works in accordance with applicable international standards, project specifications, and client requirements. 3. Scope of Work 3.1 General Description The Contractor shall provide a complete service package, including but not limited to: Project management and engineering Design of rock berms and stabilization measures Procurement and supply of rock material Mobilization and demobilization of specialized vessels and equipment Execution of rock installation works Pre- and post-installation surveys Quality assurance and as-built documentation. 3.2 Project Engineering & Management Project Planning: Develop detailed project schedules, installation plans, and risk assessments. Design Services: Prepare or review CPS berm designs, including cross-sections, material specifications, and installation tolerances. The Contractor may advise on optimal design solutions from an operational perspective. Quality Management: Implement a project-specific Quality Management System (QMS) in line with ISO 9001:2015, ensuring all works meet client and regulatory standards. HSE Management: Develop and enforce a Health, Safety, and Environmental (HSE) plan, including job hazard analysis, toolbox talks, and stop-work authority for all personnel. 3.3 Design Requirements Example (will be defined case by case by specific project): Berm Geometry: Typical berm dimensions may include heights of ~1.1 m, widths of ~0.3 m, and slopes of 1:3, subject to project-specific requirements. Material Specification: Use freshly crushed rock, grading CP 45/180 or as specified, with a specific density of ~2.65 t/m³ and bulk density of ~1.56 t/m³. All rock must comply with EN 13383-1,2 standards. Tolerances: Vertical tolerance: -0.00/+0.50 m; Horizontal tolerance: -0.00/+2.00 m either side. Tolerances are to be verified by survey. Losses and Settlement: Account for installation losses (e.g., soil penetration, settlement, wash-away, compaction) in the design and quantity calculations. Execution Accuracy: Capable of precise berm installation according to design profile; Vertical Installation Tolerance -0,00/+0,50m 3.4 Mobilization & Demobilization Mobilization: Prepare and mobilize the designated rock installation vessel(s) at the port of origin. Calibrate and test all positioning, survey, and installation equipment prior to departure. Demobilization: Upon completion, demobilize all equipment and personnel, ensuring the site is left in a safe and compliant condition. 3.5 Rock Installation Operations 3.5.1 Equipment Vessels: Use dynamically positioned fall pipe vessels (DPFPV) or equivalent. Fall Pipe Systems: Deploy central and/or inclined fall pipe systems, equipped with ROVs for precise placement and monitoring. Inclined systems are used for close proximity to structures. Survey Systems: Utilize DGNSS, USBL, multibeam echosounders (MBE), and online 3D visualization packages for real-time monitoring and documentation. Vessel Requirement: Minimum DP2 fall pipe vessel 3.5.2 Sequence of Work Procurement of Rock Material: Source and stockpile rock at the designated quarry, ensuring compliance with design specifications and timely supply. Loading Operations: Load rock onto the vessel using conveyor belts or harbor cranes, with quantities verified by draft survey. Transit to Site: Sail to the offshore site, maintaining communication with client representatives. Pre-Installation Survey: Conduct detailed bathymetric and positioning surveys to establish the as-found condition of the seabed and infrastructure. Rock Placement: Execute rock dumping using DPFPV in auto-track mode, adjusting vessel speed and feeder output to achieve the required berm profile. Use ROVs and real-time monitoring tools to ensure accuracy. Intermediate Surveys: Perform check surveys during installation to monitor progress and adjust methodology as needed. Post-Installation Survey: Conduct final surveys to verify that the installed berm meets design specifications. Demobilization: Recover all equipment and return to port. 3.5.3 Special Operations Close Proximity Works: For rock placement near structures, use inclined fall pipe or tremie pipe systems, with standoff distances and positioning monitored by echo sounders and sonar. Remedial Works: If required, perform additional passes or remedial installations based on survey results. 3.6 Survey and Documentation Survey Deliverables: Provide as-built charts (DWG, PDF), DTM ASCII files, and comprehensive as-built reports. All data must be corrected for tide and quality-checked before submission. Acceptance: Survey data and as-built documentation are to be reviewed and accepted by the client’s offshore representative before demobilization. The exact requirements will be specified by the specific case and project. ___ All companies affiliated with EnBW within the meaning of Sections 15 et seq. of the German Stock Corporation Act (AktG) shall be entitled to place orders.

      Qualification system
      Dec 16, 2028(100+ days)