Hinkismäki Electrode boiler procurement
Awarded
The competition has ended and a winner has been selected.
- Award
- Quality 20%
- Procedure
- With negotiationTwo stages
- Agreement
- Construction workover 30 months
Brief
KSS Energia Oy has entered into an agreement with Parat Halvorsen As for the delivery of an electrode boiler plant with an output of approximately 40 MW, including all necessary equipment and systems for a fully functional and operational unit, to be delivered in Kymenlaakso, Finland. The contract has a duration of 30 months and an estimated value of 2,098,000 €. The electrode boiler must meet Finnish laws, regulations, norms, and authority requirements, including the grid code specifications for demand connections (KJV2026) and must be capable of participating in the Frequency Containment Reserves (FCR). Three bids were received for this contract.
Elektrisitet og energiforvaltning
Result
- Parat Halvorsen ASWinner
- 3Number of bids
- €2,098,000Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Qualification requirements
Description
Kandidatens økonomiske forhold må være tilstrekkelige i forhold til anskaffelsens størrelse og kvalitet. Kandidatens finansielle situasjon må være minst A (kredittverdig) i Dun & Bradstreet sin ratingklassifisering, eller minst A+ (tilfredsstillende+) i Suomen Asiakastieto Oy’s Rating Alfa-klassifisering, eller tilsvarende i henhold til årsregnskap eller andre lignende rapporter. Kandidater hvis kredittvurdering er under de ovennevnte vurderingene vil bli ekskludert fra anskaffelsesprosedyren dersom kandidaten ikke kan gi en pålitelig forklaring på tiltakene den tar eller har tatt for å forbedre sin finansielle situasjon.
Documentation Requirement
Ikke spesifisert.
Source
No source found in the documents. Check the requirement against the tender documents.
Award Criteria
Description
The Procurement Unit estimates that the weighting for price will be 70–90 %. The Procurement Unit reserves the right to adjust this weighting during the negotiation procedure within the aforementioned range.
Source
No source found in the documents. Check the weight against the tender documents.
Description
The Procurement Unit estimates that the weighting for quality will be 10–30 %. Preliminary quality criteria include the supplier's delivery time and FCR performance level or response speed. The Procurement Unit reserves the right to adjust the weighting within the aforementioned range and criteria for assessing quality at later stages of the negotiation procedure.
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at KSS Energia Oy
From the notice
KSS Energia Oy (later "KSS" or "Procurement Unit") is planning the purchase of an electrode boiler to produce district heat. It is initially estimated that the electrode boiler plant will produce district heating with an output of approx. 40 MW. The procurement will cover also any relevant equipment, systems and procurements needed for fully functional and operational electrode boiler. Candidates should also note that, if higher quality water treatment system is needed by the electrode boiler, this water treatment system, including make-up water tank, pumps and all other necessary equipment to produce make-up water for the boiler is included in the scope of the Supplier . Any party participating in the procurement must note that the KSS 's electricity grid is subject to the following constraints: Supply voltage 10 kV IT, no neutral point available. The electrode boiler must withstand, at minimum, a short circuit current of 28 kA for 1 second (Ith). Fimpec Engineering Oy, a part of Sweco, is a consulting engineering company that provides qualified consulting services with a high knowledge content in Finland. Fimpec is working together with KSS to advance the project to a maturity level where investment decision can be made. PRELIMINARY PROJECT SCHEDULE Submission of Applications, April 2026 Selection of Tenderers, April 2026 Submission of Preliminary Request for Quotation, May 2026 Negotiations, May to July 2026 Submission of Final Request for Quotation, August 2026 Contract award, September 2026 The delivery must be ready for commissioning no later than the 2027–2028 heating season. The procurement is subject to an approved investment decision. The candidate shall ensure that the design, supply and erection of the electrode boiler shall fulfil the mandatory laws, regulations, norms and authority requirements which are applicable in Finland at the time of the delivery. In particular, the candidate should note that the electrode boiler must meet the requirements of the grid code specifications for demand connections (KJV2026), which are estimated to be in force at the time of delivery. The electrode boiler must be capable of participating in the Frequency Containment Reserves (FCR). The technical specifications for FCR and KJV2026 are available on the website of Finland’s transmission system operator (www.fingrid.fi/en)Main features of the procedureThe procurement will take place in compliance with Finnish legislation on procurement for contracting authorities operating in water and energy supply, transportation and postal services (Finnish Statute Series No 1398/2016, hereinafter Act on Public Contracts in Special Sectors). The estimated value of the contract exceeds the EU threshold. This procurement will be conducted as a negotiated procedure in accordance with the Act on Public Contracts in Special Sectors. Accordingly, in the first stage of the procurement procedure candidates are asked to submit applications for participation in the negotiated procedure. Only a candidate who meets the minimum requirements set in this invitation to participate can be selected for the second stage of the procurement. This second stage is called the negotiation stage. Selection of Candidates All applicants will be officially informed of the selection results for the second stage (negotiation stage). A minimum of three (3) and a maximum of four (4) candidates will be selected for negotiations. If there are fewer than three (3) suitable candidates, the Procurement Unit may continue the procurement procedure with the suitable candidates. If more than four (4) candidates submit an acceptable application, the selection will be decided based on the total combined nominal electrical capacity (MWe) of the submitted reference projects. Candidates may submit a total maximum of eight (8) references, which includes the two (2) mandatory minimum references and a maximum of six (6) additional references. To be included in the comparison, all references must meet the mandatory minimum requirements . The candidates will be ranked according to the total combined nominal electrical capacity (MWe) of all their accepted reference projects (up to the maximum of eight). The four (4) candidates with the highest combined capacities will be selected to proceed to the negotiation stage. If candidates whose ranking determines selection to the negotiation stage have identical combined capacities, the ranking will be decided by lottery conducted by the Procurement Unit. Description of the negotiations The candidates select for negotiations are asked to submit preliminary quotations based on the preliminary request for quotation before the negotiations. Based on the preliminary quotations, the scope and content of the negotiations will be determined. All terms of the agreement are open for negotiation. The candidates selected for negotiations will be sent invitation to negotiate and a meeting schedule before the negotiations begin. The negotiation meetings will be held remotely (Teams or similar). The language of the negotiations is English, but if the parties so agree, the negotiations may also be conducted in Finnish, however, all minutes shall be drafted in English. Candidates are not compensated for preparing and submitting a participation application or tender, participating in negotiations, presenting or otherwise participating in other procedures. The candidate is responsible for the costs of participating in the procedure. Invitation to participate and its materials are provided in English. Some supplementary documents will be submitted in Finnish, but English translations of these documents may be provided if needed.
Contact
kari.dansk@kssenergia.fi- Result · PrequalificationType
- KymenlaaksoLocation
- 45251000Main codeConstruction works for power plants and heating plants
- 42160000Boiler installations42161000Hot-water boilers