Netherlands: Tenders/N.V. HVC/HVC - Battery Energy Storage System (BESS) - Alkmaar
  1. Competition notice published

    Aug 25, 2025 4:57 AMAugust 25, 2025 4:57 AM
  2. Questions deadline

    Sep 12, 2025 2:00 PMSeptember 12, 2025 2:00 PM
  3. Qualification deadline

    Sep 30, 2025 2:00 PMSeptember 30, 2025 2:00 PM
  4. Invitation to submit tender

    Oct 23, 2025 10:00 PMOctober 23, 2025 10:00 PM
  5. Tender submission deadline

    Comes with the invitation
  6. Contract start date

    Mar 2, 12:00 AMMarch 2, 2026 12:00 AM
  7. Contract end date

    Mar 2, 2027 12:00 AMMarch 2, 2027 12:00 AM

Brief

HVC - Battery Energy Storage System (BESS) - Alkmaar

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Sep 30, 2025Expired
Procedure
With prequalificationTwo stages
Agreement
Construction work
Estimated value
€10Muntil Mar 2027

Brief

The design, engineering, construction, installation, commissioning and maintenance of a (at least) 15 MW (at connection point) and at least 30 MWh usable capacity Battery Energy Storage System connected to the existing grid connection of HVC Alkmaar on the available free fields. Based on a full-scope turnkey EPC contract, including the BESS (battery modules, inverters, transformers, control cabinets, auxiliary equipment, network equipment), civil works (foundation, digging, fencing, security), cabling supply and laying, connection to the grid connection and battery management system (BMS). The contract should include adequate quality and performance warranties and additionally an O&M contract including the maintenance of the BESS. The fencing, gates and camera security system of the BESS is also part of the EPC contract, to be taken over by HVC asset management at the take-over date. These items won’t be part of the O&M contract Also requested, but optional, is the delivery of an Energy Management System (EMS) with communication interface to monitor BESS usage in relation to the existing plant and the grid connection limits. The Client will provide required planning and construction permits from the municipality, and permits for the HDD drilling to the grid connection. The Client will provide access to the grid connection. Contractor will have to liaise with the authorized personnel of the Client to ensure safe and reliable connection of the BESS to the existing plant.

Elektrisk infrastruktur og veibelysning

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at N.V. HVC

From the notice

  • The design, engineering, construction, installation, commissioning and maintenance of a (at least) 15 MW (at connection point) and at least 30 MWh usable capacity Battery Energy Storage System connected to the existing grid connection of HVC Alkmaar on the available free fields. Based on a full-scope turnkey EPC contract, including the BESS (battery modules, inverters, transformers, control cabinets, auxiliary equipment, network equipment), civil works (foundation, digging, fencing, security), cabling supply and laying, connection to the grid connection and battery management system (BMS). The contract should include adequate quality and performance warranties and additionally an O&M contract including the maintenance of the BESS. The fencing, gates and camera security system of the BESS is also part of the EPC contract, to be taken over by HVC asset management at the take-over date. These items won’t be part of the O&M contract Also requested, but optional, is the delivery of an Energy Management System (EMS) with communication interface to monitor BESS usage in relation to the existing plant and the grid connection limits. The Client will provide required planning and construction permits from the municipality, and permits for the HDD drilling to the grid connection. The Client will provide access to the grid connection. Contractor will have to liaise with the authorized personnel of the Client to ensure safe and reliable connection of the BESS to the existing plant.Main features of the procedureEuropean restricted Tender

  • Contact

    Lars van der Veldenl.vandervelden@hvcgroep.nl
  • Type
    Competition · Prequalification
  • Location
    Alkmaar en omgeving
  • Main code
    Electrical installation work
    45310000
  • 31440000Batteries45200000Works for complete or part construction and civil engineering work45230000Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork45232200Ancillary works for electricity power lines45311000Electrical wiring and fitting work

Similar active competitions

  • Slovenské elektrárne, a.s.

    Batterisystemer og energilagring

    Implementation of Battery Energy Storage System at Čierny Váh

    Slovenské elektrárne, a.s. seeks an EPC contractor to design, permit, supply, install, commission and put into operation a battery energy storage system at Čierny Váh in the Žilinský Region, over approximately 1,234 days. The BESS must provide at least 480 MWh of usable capacity and 120 MW of rated power, connect to the 400 kV substation through a new 400 kV bay, and support frequency reserves, electricity-market services, frequency-response functions and island operation to maintain the pumped-storage plant’s auxiliary supply during loss of its 22 kV connection. The scope includes civil, electrical and mechanical works; battery containers, conversion and control systems, transformers, switchgear and related equipment; integration with existing plant systems; protection, monitoring, communications, fire safety and security; and testing, performance verification, operational training and documentation needed for safe, reliable operation. The contract will be awarded solely on the lowest total price excluding VAT.

    Competition with qualification
    Nov 30, 2026(12 days)
  • Alliander N.V.

    Batterisystemer og energilagring

    Market Consultation Utility Connect - Power Back-up

    Alliander N.V. is planning the procurement of a 48VDC power backup solution for antenna sites and PoP locations, capable of providing 24 hours of power autonomy, to be installed within their Site Support Cabinet (SSC). Suppliers are invited to provide feedback on the feasibility of the assumptions and propose alternative solutions that meet the buyer's objectives.

    Planning€4,900,000
  • Teplárna České Budějovice, a.s.

    Elektrisk infrastruktur og veibelysning

    Dodávka bateriového úložiště

    Teplárna České Budějovice, a.s. potřebuje v Jihočeském kraji dodat a namontovat bateriové úložiště s maximální celkovou hodnotou 62 milionů Kč. Zakázka zahrnuje dva bateriové kontejnery a dvě trafostanice, elektroinstalaci pro připojení úložiště a řízení jeho technologií pro poskytování podpůrných služeb výkonové rovnováhy sítě. Součástí je také zpracování a posouzení projektové dokumentace pro provádění stavby, dodávka a montáž všech projektovaných komponent a související práce a služby. Nabídky budou hodnoceny výhradně podle ceny; rozhoduje nejnižší nabídková cena bez DPH.

    Competition
    Dec 7, 2026(19 days)
    CZK 62,000,000