Notice of Suspension TSE/Neste Heat Pump System
Cancelled
The competition has been cancelled.
- Qualification deadline
- 25. okt. 2020Expired
- Award
- Coefficient of performance 15% and 3 more
Brief
Turun Seudun Energiantuotanto Oy (TSE) was planning to build a heat pump plant for district heating production. The heat pump would have used cooling water from an industrial site as a heat source. The estimated heat output of the heat pump system would have been around 40 — 60 MW and the heat would have been transferred to the local district heating network. This supply would have consisted of the heat pump plant with the necessary auxiliary equipment. As the future of the industrial site and thus the availability of the heat source is unsure, the procurement of the heat pumps is suspended.
Anleggsmaskiner og utstyr
Result
- Reason for cancellationAnnet
- 0Number of bids
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Source
No source found in the documents. Check the weight against the tender documents.
Description
Coefficient of performance
Source
No source found in the documents. Check the weight against the tender documents.
Description
Technical level of supply
Source
No source found in the documents. Check the weight against the tender documents.
Description
Management and technical skills
Source
No source found in the documents. Check the weight against the tender documents.
Description
Resources
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Turun Seudun Energiantuotanto Oy
From the notice
Turun Seudun Energiantuotanto Oy (TSE) was planning to build a heat pump plant for district heating production. The heat pump would have used cooling water from an industrial site as a heat source. The estimated heat output of the heat pump system would have been around 40 — 60 MW and the heat would have been transferred to the local district heating network. This supply would have consisted of the heat pump plant with the necessary auxiliary equipment. As the future of the industrial site and thus the availability of the heat source is unsure, the procurement of the heat pumps is suspended.
Contact
Tapani Bastmantapani.bastman@tset.fi- Result · PrequalificationType
- 42511110Main codeHeat pumps