Owner's Engineering Services for Hydrogen Transmission Pipeline Projects
Awarded
The competition has ended and a winner has been selected.
- Qualification deadline
- Mar 27, 2025Expired
- Award
- Price 40%
Brief
Gasgrid Finland Oy and its subsidiary company Gasgrid Vetyverkot Oy (both later referred to as "Gasgrid") are developing the hydrogen transmission infrastructure to promote Finland’s role in the hydrogen economy. Gasgrid has initiated a number of hydrogen infrastructure development projects in Finland and in the Baltic Sea area to strengthen energy self-sufficiency and to promote the creation of hydrogen economy investments in Finland. The procurement covers the Owner’s Engineering services for the hydrogen transmission pipeline projects (later “OE services”). The main purpose of the OE services is to ensure that the engineering and construction of the onshore and station projects and offshore projects are implemented in accordance with a high standard of workmanship and quality, on project schedule, and within a budget. The OE services will consist of two separate parts: Part 1: OE services for onshore projects (Part 1) and Part 2: OE partner for offshore projects (Part 2) Gasgrid will select two (2) partners for Owner’s Engineering services. Gasgrid will select one OE partner as per each part of the procurement. The services are described in more detail in the Invitation to Participate and its annexes. The main contracting entity in this procurement is Gasgrid Vetyverkot Oy. Gasgrid Finland Oy may purchase services from the service provider(s) to the specific needs relating to the development and implementation of the hydrogen transmission network described in the scope of service. The contracting entities participate also in cross-border projects aiming at building cross-border hydrogen infrastructures, covering for example Nordic Hydrogen Route, Nordic-Baltic Hydrogen Corridor and Baltic Sea Hydrogen Collector. The cross-border projects are covered by the scope of this procurement to the extent the contracting entities are responsible for the technical design, the management of the design, and building of the cross-border infrastructures. The contracting entities may assign or transfer the agreement or parts thereof to a company or companies or to other joint organisation(s) of the cross-border projects which may be established for the implementation of the projects at a later stage as the projects progress. The contracting entities of this procurement may assign or transfer the agreement or parts thereof for the implementation of the tasks and shares for which the contracting entities are responsible. Gasgrid will apply CEF funding for the hydrogen projects. If Gasgrid is granted funding, Gasgrid will implement the necessary changes to the contracts as required by the funding instrument. Procurement documents are made available to candidates in the following electronic procurement system: https://www.esourcing2.fi/prod/Account/logon To register in the electronic procurement system, the candidate must first provide the necessary contact information at https://www.esourcing2.fi/prod/dist/signup/supplier/gasgrid After registration, the candidate will be provided with the necessary information to log into the system.
Rådgivende ingeniørtjenester for bygg og anlegg
Result
- StreamTec Solutions AGWinner
- Worley Nederland B.V.Winner
- 4Number of bids
- €6,893,145Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Professional experience of the nominated team members (exceeding the minimum requirements) and the Engineering Management Plan for feasibility and basic engineering phases were evaluated. The Contracting Authority evaluated different aspects of engineering management, such as organising and resourcing, scheduling, processes and risk management. The overall comparison method was defined in more detail in the invitation to tender.
Evaluation Method
Professional experience of the nominated team members (exceeding the minimum requirements) 50 %: The professional experience of the following key persons in accordance with the weightings given in the CV Form were evaluated: Engineering manager, Process engineer, Piping and layout engineer, Technical safety engineer, Compressor engineer, Pipeline engineer, routing, Pipeline engineer, geophysics and surveying, Instrumentation and automation engineer, Process electrification engineer, Civil and structural engineer, Pipeline engineer, materials and design, Pipeline engineer, subsea installations, Civil engineer, landfall design. Engineering Management Plan, 10%: The tenderer’s engineering management plan for feasibility and basic engineering phases were evaluated as part of the quality comparison. The Contracting Authority evaluated the different aspects of the engineering management, such as organising and resourcing, scheduling, processes and risk management.
Sub-criteria
- Professional experience of team members83%
The professional experience of the nominated key persons (exceeding the minimum requirements) in accordance with the weightings given in the CV Form were evaluated. Key persons include: Engineering manager, Process engineer, Piping and layout engineer, Technical safety engineer, Compressor engineer, Pipeline engineer, routing, Pipeline engineer, geophysics and surveying, Instrumentation and automation engineer, Process electrification engineer, Civil and structural engineer, Pipeline engineer, materials and design, Pipeline engineer, subsea installations, Civil engineer, landfall design.
- Engineering Management Plan17%
The tenderer’s engineering management plan for feasibility and basic engineering phases were evaluated as part of the quality comparison. The Contracting Authority evaluated the different aspects of the engineering management, such as organising and resourcing, scheduling, processes and risk management.
Source
No source found in the documents. Check the weight against the tender documents.
Description
The prices were to be provided in the format specified in the Price Sheet (Annex 3A and 3B). The price points were calculated using a standardization method: for each tender 𝑥, the expected value 𝜇 is subtracted, and the resulting difference is divided by the variance 𝜎. The overall comparison method was defined in more detail in the invitation to tender.
Evaluation Method
The price points were calculated using a standardization method: for each tender 𝑥, the expected value 𝜇 is subtracted, and the resulting difference is divided by the variance 𝜎.
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Gasgrid vetyverkot Oy
From the notice
Gasgrid Finland Oy and its subsidiary company Gasgrid Vetyverkot Oy (both later referred to as "Gasgrid") are developing the hydrogen transmission infrastructure to promote Finland’s role in the hydrogen economy. Gasgrid has initiated a number of hydrogen infrastructure development projects in Finland and in the Baltic Sea area to strengthen energy self-sufficiency and to promote the creation of hydrogen economy investments in Finland. The procurement covers the Owner’s Engineering services for the hydrogen transmission pipeline projects (later “OE services”). The main purpose of the OE services is to ensure that the engineering and construction of the onshore and station projects and offshore projects are implemented in accordance with a high standard of workmanship and quality, on project schedule, and within a budget. The OE services will consist of two separate parts: Part 1: OE services for onshore projects (Part 1) and Part 2: OE partner for offshore projects (Part 2) Gasgrid will select two (2) partners for Owner’s Engineering services. Gasgrid will select one OE partner as per each part of the procurement. The services are described in more detail in the Invitation to Participate and its annexes. The main contracting entity in this procurement is Gasgrid Vetyverkot Oy. Gasgrid Finland Oy may purchase services from the service provider(s) to the specific needs relating to the development and implementation of the hydrogen transmission network described in the scope of service. The contracting entities participate also in cross-border projects aiming at building cross-border hydrogen infrastructures, covering for example Nordic Hydrogen Route, Nordic-Baltic Hydrogen Corridor and Baltic Sea Hydrogen Collector. The cross-border projects are covered by the scope of this procurement to the extent the contracting entities are responsible for the technical design, the management of the design, and building of the cross-border infrastructures. The contracting entities may assign or transfer the agreement or parts thereof to a company or companies or to other joint organisation(s) of the cross-border projects which may be established for the implementation of the projects at a later stage as the projects progress. The contracting entities of this procurement may assign or transfer the agreement or parts thereof for the implementation of the tasks and shares for which the contracting entities are responsible. Gasgrid will apply CEF funding for the hydrogen projects. If Gasgrid is granted funding, Gasgrid will implement the necessary changes to the contracts as required by the funding instrument. Procurement documents are made available to candidates in the following electronic procurement system: https://www.esourcing2.fi/prod/Account/logon To register in the electronic procurement system, the candidate must first provide the necessary contact information at https://www.esourcing2.fi/prod/dist/signup/supplier/gasgrid After registration, the candidate will be provided with the necessary information to log into the system.Main features of the procedureThe procurement procedure is a negotiated procedure with prior call for competition. In negotiated procedures with prior call for competition, any economic operator may submit a request to participate in response to a call for competition by providing the information for qualitative selection that is requested by the contracting entity. Only those economic operators invited by the contracting entity following its assessment of the information provided may participate in the negotiations.
Contact
riikka.olkkonen@gasgrid.fi- Result · PrequalificationType
- 71300000Main codeEngineering services
- 71310000Consultative engineering and construction services71320000Engineering design services71336000Engineering support services71630000Technical inspection and testing services