Search
  • Search


    Purchase of 220 kV AC underground cables, accessories, supervision and jointing work for three cable systems (with approximate 90 km total length for all systems)

    Energinet Eltransmission A/S

    Purchase of 220 kV AC underground cables, accessories, supervision and jointing work for three cable systems (with approximate 90 km total length for all systems)

    1. Competition notice published

      Feb 5, 2025 12:09 PMFebruary 5, 2025 12:09 PM
    2. Contract start date

      Sep 2, 2025 12:00 AMSeptember 2, 2025 12:00 AM
    3. Contract signed

      Dec 10, 2025 12:00 AMDecember 10, 2025 12:00 AM
    4. Result notice published

      Dec 17, 2025 10:18 AMDecember 17, 2025 10:18 AM
    5. Contract end date

      Apr 1, 2031 12:00 AMApril 1, 2031 12:00 AM

    Brief

    Denmark: Tenders/Energinet Eltransmission A/S/Purchase of 220 kV AC underground cables, accessories, supervision and jointing work for three cable systems (with approximate 90 km total length for all systems)

    Awarded

    The competition has ended and a winner has been selected.

    Qualification deadline
    Dec 16, 2025Expired
    Award
    Organization and Key Personnel and Programme 15% and 3 more
    Procedure
    With negotiationTwo stages
    Agreement
    Buying goods
    Estimated value
    €55.5Muntil Apr 2031

    Brief

    Energinet Eltransmission A/S har inngått en avtale med LS Cable & System Ltd om å levere 220 kV AC jordkabler, tilbehør, veiledning og skjøtearbeid for tre kabelsystemer, med en total lengde på cirka 90 km, som skal installeres i den sørlige og østlige delen av Sjælland, Lolland og Falster, Danmark. Avtalen har en verdi på 36 369 075 EUR. Det ble mottatt 3 tilbud i konkurransen.

    Elektrisk utstyr og belysning

    Result

    TED
    • LS Cable & System Ltd
      Winner
    • Number of bids
      3
    • Contract value
      €36,369,075

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Qualification requirements

    • Description

      Egenkapital fra siste årsrapport må, på tidspunktet for prekvalifisering, være minst 18 500 000,00 EUR.

      Documentation Requirement

      Søkeren må bekrefte økonomisk evne i ESPD del IV.B med informasjon fra siste årsrapport angående egenkapital (total egenkapital inkl. aksjekapital, reserver, revaluering, tilbakeholdt fortjeneste osv.). Hvis søkeren baserer seg på kapasiteten til andre enheter eller søkeren er en gruppe økonomiske aktører, må informasjonen for ESPD del IV.B også gis i en separat ESPD fra hver av disse enhetene. Det er søkerens eget ansvar å sikre at minimumskravene nås basert på konsolidering når søkeren baserer seg på kapasiteten til andre enheter eller når søkeren er en gruppe økonomiske aktører.

      Source

      No source found in the documents. Check the requirement against the tender documents.

    • Description

      Egenkapitalandelen fra siste årsrapport må, på tidspunktet for prekvalifisering, være minst 20 %. Hvis egenkapitalandelen er mellom 15 % og 20 %, kan søkeren kvalifisere dersom egenkapitalen overstiger 55 700 000,00 EUR.

      Documentation Requirement

      Søkeren må bekrefte økonomisk evne i ESPD del IV.B med informasjon fra siste årsrapport angående egenkapitalandel (egenkapital/totale eiendeler). Dette må oppgis med to desimaler. Hvis søkeren baserer seg på kapasiteten til andre enheter eller søkeren er en gruppe økonomiske aktører, må informasjonen for ESPD del IV.B også gis i en separat ESPD fra hver av disse enhetene. Det er søkerens eget ansvar å sikre at minimumskravene nås basert på konsolidering når søkeren baserer seg på kapasiteten til andre enheter eller når søkeren er en gruppe økonomiske aktører.

      Source

      No source found in the documents. Check the requirement against the tender documents.

    • Description

      Søkeren kan levere opptil 3 (tre) mest sammenlignbare og relevante referanser utført de siste 5 (fem) årene som del av søknaden. Med «utført de siste 5 årene» menes at referansen ikke må være fullført før datoen som nås når man teller 5 år tilbake fra innleveringsdatoen for prekvalifisering. Referanser eldre enn dette vil ikke bli tatt i betraktning. Referanser som ennå ikke er fullført kan inkluderes som del av søknaden, men søkeren må beskrive de delene som ennå ikke er levert, og dette kan påvirke vurderingen av søkeren. Hvis referanser er innhentet i samarbeid med andre parter, bør søkeren tydelig forklare hvilke elementer som er utført av søkeren. Referansene skal beskrive 220 kV (eller høyere) underjordiske kabelsystemer.

      Documentation Requirement

      Evnen vil bli vurdert basert på referanser som kan fylles ut i ESPD del IV.C. Referansene skal inkludere: en spesifikk beskrivelse av leveranser, inkludert spenningsnivå, kabellengde, maksimale leveringslengder og utførte oppgaver (f.eks. design, fabrikasjon, fabrikktesting, levering, transport, konstruksjon (ikke sivile arbeider), installasjon (skjøter og AIS-termineringer, koblingsbokser), ferdigstillelse, testing på stedet, igangkjøring og overtakelsestesting av hele leveransen og dens systemer og funksjoner); beskrivelse av typeprøve (hvis utført), inkludert spenningsnivå ved halvledende lag; produksjons- og testanlegg for strømkablene; produksjons- og testanlegg for tilbehøret; leveringssted; informasjon om kontaktdata (navn, e-post og telefonnummer) for referanser; kontraktsverdi (hvis mulig); dato for igangsetting og endelig levering (dag, måned, år). Eventuelle uklarheter og/eller uforståeligheter kan ha en negativ effekt på vurderingen. Hvis søkeren baserer seg på kapasiteten til andre enheter eller søkeren er en gruppe økonomiske aktører, må det maksimale antallet referanser fortsatt respekteres og kan ikke overstige 3 når de kombineres. Hvis flere sendes inn, vil oppdragsgiveren kun vurdere de nyeste referansene bestemt av dato for endelig levering, i dette tilfellet vil ikke uferdige referanser bli inkludert. Hvis søkeren baserer seg på andre enheters kapasitet eller er del av en gruppe økonomiske aktører, må informasjonen om ESPD del IV.C sendes inn i separate ESPD-er for hver enhet.

      Source

      No source found in the documents. Check the requirement against the tender documents.

    Award Criteria

    • Description

      Prices must be stated in the attached schedule of prices and the defined price elements must be completed herein. Prices must be stated exclusive of VAT, but inclusive of all other expenses associated with the purchase. The Carbon Footprint Tool (doc. no. 24/02180-13 “Carbon Footprint Tool”) should be completed as instructed in doc. no. 24/02180-14 “Rules regarding Carbon Footprint Tool”. The sum of climate change impact (ton CO2 footprint) in the “Summary” fan should be transferred to the Schedule of Prices fan “Preliminaries” Pos. 3.4 Prices must be stated in EUR.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      Programme: For the evaluation of the “Project Programme” the tenderer should include a detailed and robust project specific programme which outlines how the activities will be planned from contract commencement date until taking-over certificate has been issued. The Project Programme shall honour doc. no. 24/02180-17 “Preliminary Time Schedule” included in the tender material. The documentation should include a detailed description of how the identified activities are planned and executed. Fur-ther, a GANTT-chart out-lining the overall time schedule should be submitted. Concerning the activities on site in Denmark the tenderer should include a detailed description of the manpower used on site for supervision and jointing work. Reference is made to doc. no. 24/02180-17 “Preliminary Time Schedule” and should include detailed planning of the supervision activities and jointing work on site.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      The evaluation will be based on a description of the offered Technical Solution. The description should demonstrate the technical level of the, and include these elements: 1. Description of the complete system design (including engineering, design, documentation, and calculations) and the robustness of the mechanical design cf. technical requirements (24/02180-5) All requested data, cf. EGS-0084 and EGS-0085. The installation process will also be part of the evaluation and will be based on the submitted installation process of accessories and of testing during the installation as described in “SLF02 – procurement of 220 kV underground cable systems – Technical requirements” paragraph 5. Where more than values are required, the technical level should be explained in detail for each element as any ambiguities, missing information or uncertainties relating to the performance or characteristics of the offered solution may have a negative effect on the tender evaluation.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      An overall evaluation will be made of this sub-criterion.

      Source

      No source found in the documents. Check the weight against the tender documents.

    • Description

      For the purpose of evaluation, the tenderer may propose deviations to the contract terms not identified as mandatory parts cf. section 3.7.1. The contract terms are considered: • Contract Agreement (doc. No. 24/02180-24) • Appendix 1: General Terms and Conditions for Purchase (doc. No. 24/02180-23), If the tenderer wishes to propose deviations these should be stated in doc. no. 24/02180-19 - Clarification lists The proposed deviations to the contract terms must be stated in the spreadsheet marked “Legal clarification”. The proposed deviations should be explicit and with explanation as to why they are made.

      Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Energinet Eltransmission A/S

    From the notice

    • The Contracting Authority wants to purchase 220 kV AC underground cables, accessories, supervision and jointing work for three cable systems (with approximate 90 km total length for all systems) to be installed in the south and eastern part of Zealand, Lolland and Falster, Denmark.

    • Contact

      Procurement - Aprocurement@energinet.dk
    • Type
      Result · Prequalification
    • Main code
      High-voltage cable
      31321300
    • 31300000Insulated wire and cable31320000Power distribution cables31340000Insulated cable accessories31343000Insulated cable joints

    Similar active competitions

    • Energinet Eltransmission A/S

      Diverse konstruksjonsmateriell

      Re-tendering - Framework agreement: Purchase of fittings for glass insulator strings 26/17723

      Energinet Eltransmission A/S needs to purchase complete glass insulator strings through a framework agreement over 4 years, with two options for extension of 2 years each, for a total potential duration of 8 years. The maximum total value of the agreement is 30,442,953 EUR. The procurement is divided into two lots: Lot 1 for complete glass insulator strings for powerlines, with an expected consumption of 10,000,000 EUR and a maximum value of 24,000,000 EUR; and Lot 2 for complete glass insulator strings for substations, with an expected consumption of 2,684,563.75 EUR and a maximum value of 6,442,953.00 EUR. Tenders can be submitted for one or both lots. The award criteria are Quality (41.6667%), Delivery time (16.6667% + 16.6667% = 33.3334%), and Price (25%). Qualification requirements include an equity of at least 2,500,000 EUR and an equity ratio of at least 20% (or 15-20% if equity exceeds 7,500,000 EUR) for Lot 1. Additionally, applicants must provide three to five comparable and relevant references from the past five years, with at least one reference demonstrating the supply of glass insulators for a transmission network with a voltage level of at least 132 kV.

      Framework agreement with qualification
      Nov 2, 2026(4 days)
      €30,442,953
    • KONSTANT Net A/S

      Rådgivende ingeniørtjenester for bygg og anlegg

      EU-udbud af totalrådgivning til etablering af 60 kV Søkabler, Samsø

      KONSTANT Net A/S har brug for totalrådgivning til etablering af 60 kV søkabler til Samsø, beliggende i Østjylland. Opgaven omfatter al teknisk rådgivning, herunder projektering, tilsyn, byggeledelse, forundersøgelser, myndighedsbehandling, udbud på søkabler og installation samt projektledelse frem til dokumentation og aflevering, med det formål at etablere en driftssikker 60 kV-forbindelse. Tildelingskriterierne vægtes som følger: Pris (30%), Projektorganisation inkl. nøglepersoner (40%) og Metodebeskrivelse (30%). Som kvalifikationskrav skal ansøgere have en soliditetsgrad på mindst 20% og positiv egenkapital i de seneste to regnskabsår. Derudover skal ansøgere indsende maksimalt 3 referencer fra de seneste 5 år, der dokumenterer erfaring med ledningsarbejde i maritime miljøer, herunder projektledelse, projektering, kortlægning af kabeltrace, geofysiske/geotekniske/miljømæssige forundersøgelser, myndighedsstrategi, miljøkonsekvensvurdering og arbejdsmiljøkoordinering, med særlig vægt på elektriske ledningsanlæg i spændingsniveau 30-150 kV.

      Competition with qualification
      Nov 2, 2026(4 days)
    • Nexel A/S

      Elektrisk infrastruktur og veibelysning

      Dynamisk indkøbssystem - Anskaffelse af el-tekniske ydelser inden for 30 kV og 50 kV elforsyningsarbejde

      Nexel A/S har brug for el-tekniske ydelser inden for 30 kV og 50 kV elforsyningsarbejde til en maksimal totalværdi på 30 millioner DKK over 5 år. Ydelserne omfatter kabelarbejde (mufning, flytning, endeafslutning og tilslutning af kabler), stationsarbejder (kobberarbejde, smedearbejde, stålmontage, montage af komponenter, samleskinner og forbindelser) samt el-teknisk montage i hovedstationer (montage af tavler, komponenter, relæbeskyttelse, ombygning af tavler og tegningsforståelse/oprettelse af as-build-tegninger). Tildelingskriterierne er pris (30%) og bemanding (70%), hvor sidstnævnte vurderes ud fra medarbejdernes erfaring og relevante uddannelse. Wicotec Kirkebjerg A/S har en lignende kontrakt i dag.

      Dynamic purchasing system
      Aug 2, 2029(100+ days)
      DKK 30,000,000