    RFI - Alternative Gas-insulated (SF6-free) Instrument Transfomers

    Elia Group

    RFI - Alternative Gas-insulated (SF6-free) Instrument Transfomers

    1. Planning notice published

      Dec 24, 2024 9:22 AMDecember 24, 2024 9:22 AM
    2. Questions deadline

      Jan 29, 2025 12:00 PMJanuary 29, 2025 12:00 PM

    Brief

    Belgium: Tenders/Elia Group/RFI - Alternative Gas-insulated (SF6-free) Instrument Transfomers

    Planned

    The competition has not been announced yet.

    Deadline
    Jan 29, 2025Expired
    Agreement
    Buying goods

    Brief

    RFI - market survey performed to gain insight into the market for Alternative Gas-insulated (SF6-free) Instrument Transformers

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Elia Group

    From the notice

    • RFI - market survey performed to gain insight into the market for Alternative Gas-insulated (SF6-free) Instrument Transformers

    • Contact

      Purchasingbenedikt.devos@elia.be
    • Type
      Planning
    • Location
      Berlin
    • Main code
      Substation equipment
      31682540

    Similar active competitions

    • RheinEnergie AG

      Gasisolierte druckfreie Mittelspannungsschaltanlagen

      RheinEnergie AG plant die Beschaffung von gasisolierten druckfreien Mittelspannungsschaltanlagen mit integriertem Störlichtbogenbegrenzer für sicherheitskritische Standorte oder Räume, in denen keine Druckbelastung auftreten darf.

      Planning
    • 50Hertz Transmission GmbH

      Elektrisk utstyr og belysning

      Qualification System for SF6 free Gas Insulated Switchgears (GIS) above Ur 52kV with a Global Warming Potential (GWP) <1.000

      Design, manufacturing, factory testing, supply, delivery, unloading, installation, on-site testing and commissioning as well as optionally the service and maintenance of Gas Insulated Switchgears (GIS) with (1) a Global Warming Potential (GWP) < 1 or with insulation gases not containing fluorinated greenhouse gases (Category (1)) (2) with insulation gases containing fluorinated greenhouse gases with a Global Warming Potential (GWP) ≥ 1 and < 1.000 (Category (2)) referred to in the EU Regulation on fluorinated greenhouse gases (Regulation (EU) 2024/573) including all necessary/related accessories for Rated Voltage Levels (Ur) above 52kV

      Qualification system
      Oct 15, 2027(100+ days)
    • 50Hertz Transmission GmbH

      Qualification System for SF6-free Instrument Transformers (123kV-245kV – 420kV) and Resisitive-Capacitive Dividers (123kV-245kV-420kV)

      The subject of this qualification system is the design, manufacturing, testing, packaging, transport, delivery, unloading, storage, and after sales services of SF6-free oil- or gas-insulated outdoor Instrument Transformers and Resistive-Capacity Dividers for 50Hertz (Germany) substations (referring to the EU Regulation on fluorinated greenhouse gases (Regulation (EU) 2024/573 for Rated Voltage Levels (Ur) above 52kV). The included equipment is Instrument Transformers: - 123kV 40kA gas-insulated - 245kV 50A gas-insulated - 420kV 63kA gas-insulated - 420kV 63kA oil-insulated - 420kV 80kA gas-insulated - 420kV 80kA oil-insulated Resistive-Capacitive Dividers: - 123kV gas-insulated - 123kV oil-insulated - 245kV gas-insulated - 245kV oil-insulated - 420kV gas-insulated - 420kV oil-insulated

      Qualification system
      Sep 24, 2028(100+ days)