    RFT to Modify + Install Upgraded Air Extraction Duct Work on our Coating Line T+G Area at SmartPly Europe DAC ‘26

    SmartPly Europe DAC

    RFT to Modify + Install Upgraded Air Extraction Duct Work on our Coating Line T+G Area at SmartPly Europe DAC ‘26

    1. Competition notice published

      May 15, 12:06 PMMay 15, 2026 12:06 PM
    2. Questions deadline

      May 29, 2:00 PMMay 29, 2026 2:00 PM
    3. Tender submission deadline

      Jun 5, 2:00 PMJune 5, 2026 2:00 PM
    4. Opening date

      Jun 5, 2:30 PMJune 5, 2026 2:30 PM
    5. Tender validity period

      Jun 9, 2:00 PMJune 9, 2026 2:00 PM

    Brief

    Ireland: Tenders/SmartPly Europe DAC/RFT to Modify + Install Upgraded Air Extraction Duct Work on our Coating Line T+G Area at SmartPly Europe DAC ‘26

    Expired

    The competition has expired without a winner being announced.

    Brief

    Anleggs- og infrastrukturbygging

    SmartPly Europe DAC needs engineering and construction services to modify and install an upgraded Air Extraction Duct system in the Coating Line and T+G (Tongue + Groove) area of their plant in Belview Port, Slieverue, via Waterford. The project, valued at a maximum of 90,000 EUR, will last for 1 month and involves installing and modifying ducting, removing existing ducting, providing start-up support, and commissioning. The contractor will be responsible for all installation, bracketry, lifting, safety documentation, and associated works, and must comply with the Safety, Health and Welfare at Work (Construction) Regulations 2013, providing site-specific Risk Assessments, Method Statements, Training + Induction Records, Plant Certification, and Lift Plans.

    About the bid

      SMARTPLY Europe DAC is seeking suitably qualified engineering companies to modify and install an upgraded Air Extraction Duct system in the Coating Line and T+G (Tongue + Groove) area of the plant at our site in Belview Port, Slieverue, via Waterford (X91 PX75). This system is required to improve airflow in the ducts and provide separate Bag House connections for each production line. All ducting and final detailed drawings will be supplied by Scheuch GmbH (Free Issue to the Contractor). The Contractor is responsible for all installation, bracketry, lifting, safety documentation, and associated works as detailed below. It is envisaged that the works will take place during SmartPly’s Annual Shutdown: 24th August – 4th September 2026, with pre-shutdown works permitted in the weeks prior. Due to the nature of works as set out in this tender and other maintenance + construction activity being carried out on site, these have been deemed to be "CONSTRUCTION WORK" as per the HSA's Safety, Health and Welfare at Work (Construction) Regulations 2013. The successful Bidder will operate as "CONTRACTOR" and will be required to provide site-specific Risk Assessments, Method Statements, Training + Induction Records, Plant Certification, Lift Plans, and other requested information associated with the works. Client: SmartPly – Belview Port, Slieverue, via Waterford. Contact: Ciaran Brennan – 051 831 48 PSCS Successful Bidder Detailed Scope of Works The Contractor shall provide all labour, plant, lifting equipment, access platforms, bracketry, fixings and safety documentation necessary to complete the following works: Ducting Installation + Modification (Based on Drawing AT-03570328a) • Install and modify ducting as per Scheuch GmbH drawings (green = existing, black = new). • Remove existing ducting (Ø630mm) running from the Coating Line to Bag House 01 (BH01). • Replace with new reduced-size ducting (Ø400mm) running from the T+G Line to BH01. • Install new ducting (Ø630mm) running from the Coating Line to Bag House 04 (BH04), connecting into existing ducting (Ø710mm). • Remove the ducting line fitted under the existing Ø710mm line and blank off the opening. • Install new ducting of various diameters from the Splitter Saw to BH01, connecting into the lower extraction from the two Tenor machines and the QC Saw. Removal of Existing Ducting • Removal of existing ducting. Note: This shall be recorded in the RAMS for prior approval. Lifting Equipment + Access Platforms • The Contractor is responsible for all plant, lifting equipment, and access platforms (temporary, mobile, or fixed) required to carry out the works at heights of up to 19m above ground level. Start-Up Support + Commissioning • Provide start-up support. • Offer technical support for commissioning team. Handover Documentation The Contractor shall provide: • Site-specific Risk Assessments + Method Statements (RAMS) – to be issued 21 days prior to shutdown work commencing. • Lift plans and associated safety documentation. • Training + Induction Records. • Plant Certification. • As-installed documentation (if any variation from Scheuch drawings). Health + Safety Compliance The Contractor is responsible for all EHS requirements associated with the works, including but not limited to: • Complying with site rules and the safety + health plan. • Identifying hazards and eliminating or reducing risks. • Providing site-specific induction for all workers. • Appointing a safety officer where more than 20 persons are on site. • Reporting accidents to the Authority and to the PSCS where an employee cannot perform normal work for more than three days. All works must comply with: • Safety, Health and Welfare at Work Act 2005 • General Application Regulations 2007 • Construction Regulations 2013

      Contact phone
      051 831427
      Contact email
      John.Browne@mdfosb.com
      Address
      Bellview, X91 PX75 Slieveure

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

      Found no award criteria in the contract notice.

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    SmartPly Europe DAC
    Title
    RFT to Modify + Install Upgraded Air Extraction Duct Work on our Coating Line T+G Area at SmartPly Europe DAC ‘26
    Type
    CompetitionPrequalification
    Main code
    45220000Engineering works and construction works
    Supplemental codes
    39563530Ventilation ducting44115100Ducting45350000Mechanical installations
    Location
    South-East
    Estimated value
    €90,000.00
    Duration
    1 month

    Active similar competitions

    • SmartPly Europe DAC

      Veiskilt og trafikkutstyr

      Essential Upgrade Works at SmartPly Europe DAC 26

      SmartPly Europe DAC needs construction services for minor construction work packages at its manufacturing facility in Belview, Slieveure, Waterford, Ireland. The works, with a maximum total value of 400,000 EUR, are expected to be completed over approximately four months and primarily address Health and Safety, Environmental, and operational requirements across the production facility. The project is divided into four separate lots based on the nature and type of the projects.

      CompetitionOct 5, 2026
      Oct 26, 2026(16 days)
      €400,000
    • IDA Ireland

      Rørlegger- og sanitærarbeid

      ESB Enabling Works Delivery at IDA Dundalk Science and Technology Park

      IDA Ireland needs works for the installation of ducting and chambers to enable the diversion of overhead ESB cables at IDA Dundalk Science and Technology Park in Dublin. The contract has a maximum total value of 100,000 EUR and a duration of 2 months.

      CompetitionSep 23, 2026
      Oct 22, 2026(12 days)
      €100,000
    • CBS Westland Row

      Oppføring av bygninger

      23/040 - A Qualification System for the Provision of General Building and Civil Engineering Maintenance and Repair Works to Uisce Éireann

      Uisce Éireann needs general building and civil engineering maintenance and repair works, including emergency and urgent reactive civil engineering repair and maintenance works for drinking water and wastewater networks and ancillary structures, non-reactive civil engineering repair and maintenance works for drinking water and wastewater networks and ancillary structures, non-reactive civil engineering repair and maintenance works and services associated with reservoirs, dams, tanks, pump stations, treatment works and buildings, non-reactive repair and maintenance works and services for general groundworks, including vegetation removal, site clearance works, tree felling and boundary fencing, non-reactive repair and maintenance works associated with permanent and temporary road and other surface reinstatements, and leak detection surveys.

      Qualification systemFeb 5, 2026
      May 31, 2044(100+ days)
    • Local Government Operational Procurement Centre (LGOPC)

      Rådgivende ingeniørtjenester for bygg og anlegg

      Dynamic Purchasing System for Mass Engineered Timber – Technical Advisors for Local Authorities

      The Local Government Operational Procurement Centre (LGOPC) needs technical advisory services related to Mass Engineered Timber for Local Authorities. This Dynamic Purchasing System has a maximum total value of 5,000,000 EUR over 60 months and is intended for the South-West region.

      Dynamic purchasing systemOct 5, 2026
      Feb 28, 2032(100+ days)
      €5,000,000
    • Bord na Móna PLC

      Oppføring av bygninger

      SC 07/25 - Open Cycle Gas Turbine (OCGT) and Combined Cycle Gas Turbine (CCGT) Qualification System

      Bord na Móna PLC in Ireland is establishing a Qualification System for the provision of Open Cycle Gas Turbine (OCGT) and Combined Cycle Gas Turbine (CCGT) works. This system is of indefinite duration, but is anticipated to apply for 10 years with an option to extend. The procurement covers Lot 1 – OCGT Supply OEM and LTSA, Lot 2 – OCGT Balance of Plant Constructor, Lot 3 – OCGT Engineering, Procurement and Construction (EPC) LTSA, and Lot 4 – CCGT Engineering, Procurement and Construction (EPC) + LTSA.

      Qualification systemSep 8, 2026
      Oct 6, 2029(100+ days)