Rosslare Europort, Berth 3 Upgrade
Awarded
The competition has ended and a winner has been selected.
- Procedure
- With negotiationTwo stages
- Agreement
- Construction work
- Estimated value
- €33.1Mover 3 years
Brief
Iarnród Éireann–Irish Rail has awarded BAM Contractors Limited the works contract for a 3-year upgrade of Berth 3 at Rosslare Europort, Ireland, valued at approximately €33.13 million. The project will extend the berth to accommodate larger vessels, refurbish and upgrade the linkspan, improve mooring and fendering, provide new and upgraded quayside working areas, and install onshore power supply. Six bids were received.
Result
- BAM Contractors Limited_24928Winner
- 6Number of tenders received
- €33,130,765Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Iarnród Eireann-Irish Rail
From the notice
The overall project objective is to upgrade Berth 3 in Rosslare Europort to accommodate larger vessels. The Berth 3 Upgrade project will consist of the following: • Extension to the berth to facilitate larger vessels; • Refurbishments and upgrades to the Berth 3 linkspan • Upgrade of the existing mooring and fendering on the berth • Provision of new quayside working areas and upgrades to existing areas • Provision of Onshore Power Supply (OPS) to the berth.
Contact
TBC@irishrail.ie- Result · PrequalificationType
- DublinLocation
- 45244000Main codeMarine construction works