Ireland: Tenders/Electricity Supply Board ( ESB )/TR6008 HRSG Bundles for ESB Generating Stations
  1. Competition notice published

    Nov 16, 2:58 PMNovember 16, 2026 2:58 PM
  2. Qualification deadline

    Not stated
  3. Tender submission deadline

    Nov 16, 3:58 PMNovember 16, 2026 3:58 PM

Brief

TR6008 HRSG Bundles for ESB Generating Stations

Qualification deadline
Dec 14, 20291,121 days left
Procedure
With negotiationTwo stages
Agreement
Buying services

Brief

Electricity Supply Board (ESB) is establishing a qualification system for services related to HRSG bundles at its generating stations. The notice identifies Dublin as the project location and gives no further details on the scope, contract duration, value or supplier requirements.

Rådgivende ingeniørtjenester for bygg og anlegg

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Electricity Supply Board ( ESB )

From the notice

  • TR6008 HRSG Bundles for ESB Generating Stations

  • Contact

    generationprojectsprocurement@esb.ie
  • Type
    Competition · Prequalification
  • Location
    Dublin
  • Main code
    Plant engineering design services
    71323200
  • 42160000Boiler installations42162000Steam-generating boilers42163000Steam generators

Similar active competitions

  • Electricity Supply Board ( ESB )

    Reparasjon og vedlikehold

    TR4196 ESB Poolbeg Heat Recovery Steam Generator Stack (HRSG) Works.

    Electricity Supply Board (ESB) needs works for the TR4196 ESB Poolbeg Heat Recovery Steam Generator Stack (HRSG) in Dublin. The project involves either a complete turnkey contract to replace two HRSG Stacks, including removal of existing stacks, full design of replacements, site installation, and commissioning of new mechanical rain dampers, or, at ESB's discretion, a contract to remove outer cladding and insulation and apply preservation paint coating to the exposed metal surface of both HRSG stacks (from 26.4m to 75.0m above ground).

    Qualification system
    Sep 4, 2028(100+ days)
  • Electricity Supply Board ( ESB )

    TR1675- QSQ for The Supply and Installation of Open Cycle Gas Turbine Packages within the Island of Ireland

    TR1675- QSQ for The Supply and Installation of Open Cycle Gas Turbine Packages within the Island of Ireland

    Qualification system
    Jun 13, 2027(100+ days)
  • Electricity Supply Board ( ESB )

    Elektroinstallasjon i bygninger

    TR2684 SOLAR PV SOLUTIONS

    Electricity Supply Board (ESB) needs services for Solar PV Solutions and related services to support its operations in the Republic of Ireland (ROI).

    Qualification system
    Apr 3, 2029(100+ days)