    SC 07/23 - Derrygreenagh Power 400/220 kV Substation

    Bord na Móna PLC

    SC 07/23 - Derrygreenagh Power 400/220 kV Substation

    1. Result notice published

      May 13, 6:30 AMMay 13, 2025 6:30 AM
    2. Questions deadline

      Jan 20, 11:00 AMJanuary 20, 2026 11:00 AM
    3. Tender submission deadline

      Feb 3, 11:00 AMFebruary 3, 2026 11:00 AM
    4. Contract start date

      Apr 30, 10:00 PMApril 30, 2026 10:00 PM
    5. Tender validity period

      May 3, 10:00 AMMay 3, 2026 10:00 AM

    Brief

    Ireland: Tenders/Bord na Móna PLC/SC 07/23 - Derrygreenagh Power 400/220 kV Substation

    Cancelled

    The competition has been cancelled.

    Brief

    Anleggs- og infrastrukturbygging

    Expressions of interest are invited from suitably qualified Applicants interested in being considered for the services comprise of the design, procurement, installation, and commissioning of the electrical engineering works in relation to the Derrygreenagh Power TSO substations.

    Result

    Reason for cancellation
    Besluttning av oppdragsgiveren på grunn av behovsendring
    Number of bids
    3
    Contract value
    Not stated

    About the bid

      Expressions of interest are invited from suitably qualified Applicants interested in being considered for the services comprise of the design, procurement, installation, and commissioning of the electrical engineering works in relation to the Derrygreenagh Power TSO substations.

      Contact phone
      +35345439000
      Contact email
      renewablesprocurement@bnm.ie
      Address
      Main Street, W12 XR59 Newbridge

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

      Found no award criteria in the contract notice.

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    Bord na Móna PLC
    Title
    SC 07/23 - Derrygreenagh Power 400/220 kV Substation
    Type
    ResultPrequalification
    Main code
    45220000Engineering works and construction works
    Supplemental codes
    45317300Electrical installation work of electrical distribution apparatus51110000Installation services of electrical equipment71314100Electrical services71323100Electrical power systems design services
    Location
    Dublin

    Active similar competitions

    • Electricity Supply Board ( ESB )

      Elektroinstallasjon i bygninger

      Works Associated with the Design and Build of High Voltage Electrical Substations in the Republic of Ireland

      Works Associated with the Design and Build of High Voltage Electrical Substations in the Republic of Ireland

      Qualification systemMay 2, 2024
      May 30, 2027(100+ days)
    • Bord na Móna PLC

      Elektroinstallasjon i bygninger

      CM 06/24 - Electrical Balance of Plant Qualification System

      EBoP panel creation for all upcoming grid projects. QQD to included the following Lots – Lot 1-110 KV, Lot 2 - 220 KV and Lot 3 - 400 KV.

      Qualification systemAug 29, 2024
      Sep 26, 2027(100+ days)
    • Electricity Supply Board ( ESB )

      CON1140 Qualification System for the at scale EPC delivery of 110 kV, 220 kV and 400 kV HV Substations and Substation Programmes

      ESB proposes to establish a qualification system under a negotiated procedure for the at scale EPC delivery of 110 kV, 220 kV and 400 kV HV Substations and Substation Programmes. It is envisaged that a significant number of DSO and TSO GIS Substations will be constructed during the period 2026 - 2035 and will be delivered via this procurement process as outlined in Section A Information Memorandum, attached to this publication. Substations procured under this Qualification System will include for a full end to end scope of delivery which may include in some cases site acquisition and achievement of planning permission on behalf of the Contracting Entity. The scope of substation projects under this Qualification System may include a requirement for the inclusion of additional technologies including but not limited to STATCOMS and series compensators. The First Procurement under the Qualification System is envisaged to be: • Framework for PR6 Capacity at scale EPC delivery of 110 kV and/or 110 kV to /38 kV/MV Substations and Substation Programmes. Economic Operators who wish to participate in this qualification system process should submit a response as set out in the Section A Information Memorandum document. While applications may be made to join the Qualification System at any time, those interested in being considered for the Initial Framework (the “First Procurement”) under this Qualification System should submit a completed QSQ response on or before 1200 hrs (local time) on Friday 27th June 2025 (the “First Procurement Closing Date”).

      Qualification systemMay 19, 2025
      Jun 16, 2028(100+ days)
    • Bord na Móna PLC

      Oppføring av bygninger

      AP 06/25 - Civil Balance of Plant and Civil Engineering Works for Renewable Energy Projects Qualification System

      The objective of this Qualification System is to qualify interested parties for the provision of Civil Balance of Plant and Civil Engineering Enabling Works for Renewable Energy Projects. The Qualification System is of indefinite duration. However, it is currently anticipated that the Qualification System will apply for a period of 10 years from the date of its establishment with the option to extend at the Contracting Entity’s discretion (having regard to the nature, scope and extent of services required to be undertaken). For the purposes of submitting initial Applications, Applicants must complete and return all documentation relating to their Application by the stated Application Deadline. Applicants submitting Applications will be informed at the earliest opportunity of the status of their Application. Applicants may apply for inclusion on the Qualification System at any time over the term of this arrangement. The Contracting Entity will review and evaluate Applications received after the establishment of the Qualification System on a six monthly basis.

      Qualification systemAug 9, 2024
      Sep 6, 2027(100+ days)
    • Electricity Supply Board ( ESB )

      Elektrisk infrastruktur og veibelysning

      CON1199 - Qualification System for Electrical Distribution Substation Works

      Electricity Supply Board (ESB) needs expressions of interest for a Qualification System for the subsequent procurement of engineering, civil, design, equipment and material supply, operation, maintenance, and construction services related to electrical power distribution assets, mainly within substations but also power distribution cables, ring main units, mini-pillars, and other associated assets throughout the distribution network, up to 110 kV voltage level. The works will be located in the Republic of Ireland.

      Qualification systemJun 4, 2026
      Jul 2, 2029(100+ days)