Poland: Tenders/Bechtel Polska Sp. z o. o./Temporary Warehousing Structure and Fabrication Shops (EPC) – Poland AP1000 Project
  1. Competition notice published

    Apr 3, 12:41 PMApril 3, 2026 12:41 PM
  2. Express interest deadline

    Apr 20, 3:00 PMApril 20, 2026 3:00 PM
  3. Invitation to confirm interest

    Apr 23, 10:00 PMApril 23, 2026 10:00 PM
  4. Invitation to submit tender

    Jun 22, 10:00 PMJune 22, 2026 10:00 PM
  5. Qualification deadline

    Not stated
  6. Tender submission deadline

    Comes with the invitation

Brief

Temporary Warehousing Structure and Fabrication Shops (EPC) – Poland AP1000 Project

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Apr 20,Expired
Procedure
With negotiationTwo stages
Agreement
Construction work

Brief

Bechtel Polska Sp. z o. o. needs engineering and construction services, including supply, installation, testing, and commissioning of three temporary warehousing structures (totaling 22,170 m²) and eleven temporary fabrication shops (totaling 20,735 m²) for the Poland AP1000 Project. These facilities, which are industrial standard, temporary, non-safety related, non-seismic, commercial-grade steel buildings, are intended to support construction activities for a design life of 15 years and must remain fully operational year-round in a Baltic coastal environment. The scope is limited to the buildings only, excluding furnish and production lines. All works must comply with Polish law, EU standards, and Authority Having Jurisdiction (AHJ) requirements, with the Pomeranian Voivode acting as AHJ. The seller is responsible for full design, engineering, and coordination, and the final design must be sealed by licensed Polish engineers/architects.

Industri- og lagerbygg

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Bechtel Polska Sp. z o. o.

From the notice

  • 1. Experienced and qualified Companies are invited to provide engineering and construction services, including supply, installation, testing and commissioning of Temporary Warehousing Structure and Fabrication Shops (commodity code UA11) at the project location for the Poland Nuclear Power Plant. The facilities are industrial standard, temporary, non-safety related, non-seismic, commercial-grade steel buildings, intended solely to support construction activities and not plant operations. All works must comply with Polish law, EU standards, and Authority Having Jurisdiction (AHJ) requirements, with the Pomeranian Voivode acting as AHJ. General Building Characteristics: - Structures are steel-framed, modular or pre-engineered metal buildings (PEMB). - Buildings are single-story, rectangular, low-rise, with pitched roofs. - Facilities must remain fully operational year-round in a Baltic coastal environment for a design life of 15 years. - All buildings are electric-only; no gas installations are permitted. - Uniform construction technology, finishes, and systems must be applied across all buildings for each of two types of buildings: warehouses and fabrication shops. - All furnish and production lines are excluded from the scope, the subject of the bid is limited to the solely buildings only. Temporary Warehousing Buildings – Quantity and Size 3 temporary warehouse buildings, total area 22,170 m²: - Warehouse 182: 8,400 m² (120 × 70 × 10 m) - Warehouse 183: 7,650 m² (150 × 51 × 10 m) - Warehouse 184: 6,120 m² (120 × 51 × 10 m) Structural and Architectural Requirements - Reinforced concrete slab foundations designed for heavy material handling. - Steel superstructure enclosed with insulated metal wall and roof panels. - Fire-resistant construction materials. - Concrete floor finish throughout. - Light-colored exterior siding and roofing. Functional Requirements - Areas for receiving, unpacking, sorting, staging, and “on-hold” materials. - Segregated storage for tools, instruments, piping, electrical materials, and hazardous goods. - Pallet racking, shelving, bins, and forklift-compatible aisle spacing. - Rapid roll-up material doors (minimum 6 m clearance). - Minimum four personnel/emergency exits per building. - Climate control (heating, ventilation, and cooling where required). - Access control via card, mobile app, or biometric systems. - Adequate drainage, lighting, and proximity to work fronts. - Overhead crane in the warehouse No. 184 Temporary Fabrication Shops – Quantity and Size 11 fabrication buildings, total area 20,735 m². Each building: 1,885 m² (65 × 29 × 10 m). Structural and Architectural Requirements - Reinforced concrete slab foundations. - Commercial-grade steel superstructure. - Insulated metal siding and roofing. - Fully enclosed, climate-controlled environments. - Ventilated. Functional Requirements - Fabrication lines and material handling areas. - Tool and equipment storage with secure access. - Rapid roll-up material doors and personnel exits. - Fire-resistant materials and systems. - HVAC systems. - Adequate site drainage and lighting. - Layout flexibility subject to Buyer approval. Building Systems and Installations (Applicable to All Buildings) Structural - Designed for dead, live, wind, snow loads. - Anchored steel structures on reinforced concrete slabs. Mechanical (HVAC) - Air handling units with heating, cooling, filtration, and heat recovery. - Dedicated ventilation systems for warehouses and workshops. - Electric-powered systems only. - No permanent water or sewage systems; portable handwash stations only. Fire Protection - Fire classification per Polish regulations (ZL I or as determined). - Fire alarm system. - Emergency lighting. - Internal hydrants (25 mm), fire extinguishers, fire dampers. - External hydrants with 20 dm³/s water flow. - Fire access roads and rescue provisions. Electrical - 400/230 V, 50 Hz TN-S earthing system. - Main distribution panels and sub-panels. - LED lighting (normal and emergency). - Emergency lighting minimum 90 minutes autonomy. - IP54-rated electrical enclosures. - Lightning protection per PN-EN 62305. Design, Permits, and Compliance - Seller responsible for full design, engineering, and coordination. - Final Design must be sealed by licensed Polish engineers/architects. - Compliance with Polish law, EU directives, and project specifications is mandatory. The detailed scope of work will be outlined in the specifications, scope documents, and other contractual materials provided to the Companies within the Request of Quotation.

  • Contact

    Monika Kalandykmkalandy@bechtel.com
  • Type
    Competition · Prequalification
  • Location
    Gdański
  • Main code
    Construction work for warehouses and industrial buildings
    45213200

Similar active competitions

  • BECHTEL POLSKA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ

    Bygg og anlegg - Oppføring og konstruksjon av bygninger

    Special Module Fabrication – Structural Steel – Detail, Fabrication, and Furnish (SR/US)

    BECHTEL POLSKA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ needs detailing, fabricating, and furnishing over 100 structural steel module assemblies for three nuclear power plants in Poland. The total weight of the structural steel modules is approximately 6000 metric tons. The modules include structural steel shapes, plates, studs, and miscellaneous items, primarily carbon steel with some duplex stainless steel. Fabrication is divided into five module categories: Floor modules (CAxx), Liner modules (CBxx), Heavy stair/platform tower framing (CHxx), Light stair modules (CSxx), and Platform modules (SPLxx). The first delivery is required by August 2029, with final delivery by July 2035.

    Competition
  • Bechtel Polska Sp. z o. o.

    Anleggs- og infrastrukturbygging

    Civil Construction and General Support Services

    1. Experienced and Qualified General Construction Contractors are invited to provide general construction and site support services at the project location for the Poland Nuclear Power Plant. The General Contractor shall be responsible for completing all aspects of the scope of work including, but not limited to, providing all necessary tools, equipment, labor, supervision, professional services, materials, consumables, and supplies in order to complete the following works: • Site grading for exploratory locations, maintaining surface water drainage paths, providing stable working platforms for rigs and equipment, providing and maintaining all on-site access paths for movement of drill rigs and support vehicles until the completion of field work; • Completing initial and as-built survey of investigation locations; • Backfilling the completed subsurface investigation points with cement/bentonite/grout, disposal of drill cuttings and fluids; • Maintaining the project compound (including janitorial services) and other facilities (including repairs) to ensure they remain operational, and providing additional facilities (if necessary); • Responsible for all waste disposal including general construction materials and office generated waste; • Providing support services for Subsurface Investigations activities such as: supply of fresh and potable water, supply of fuel, delivery of materials from the warehouse, relocation, reinstallation, decommissioning, repairs and maintenance of site and rig facilities; • Providing occupational health and medical services on site, including staffing licensed medical personnel, providing occupational medical care, and managing emergency care with evacuation capabilities. Responsibilities include establishing and managing a mobile fully licensed medical facility in Poland, supplying necessary pharmaceuticals and medical equipment, maintaining an electronic medical records system compliant with Polish privacy laws, and conducting drug and alcohol testing per site policies. Also providing emergency response vehicles, a mobile first aid clinic with advanced life support capabilities, and staff with advanced trauma and occupational health training. • Provide a comprehensive Health, Safety and Environmental Programme for site-wide geotechnical investigation work, including plans, procedures, training and qualified safety personnel. The detailed scope of work will be outlined in the specifications, scope documents, and other contractual materials provided to the Subcontractor within the Request of Quotation.

    Qualification system
    Jul 23, 2028(100+ days)
  • BECHTEL POLSKA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ

    Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

    CWS Circulating Water Pumps (Concrete Volute)

    BECHTEL POLSKA SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ needs the design, furnishing of materials, fabrication, testing, and delivery of nine vertical concrete volute pumps for three nuclear power plants in Poland. These pumps will circulate brackish Baltic Sea water to cool main condensers, with each pump having a rated flow of 21.3 m3/s, a pump head of 22.5m, and a design life of 60 years. The project requires physical model testing and shop performance testing. The required onsite date for Unit 1 is June 2032.

    Competition